Set 33 — Fault Currents and Breaker Ratings
Twenty worked problems that run a fault study from end to end and then spend its results. Set 18 built a five-bus \(\mathbf{Z}_{\text{bus}}\) one element at a time; that matrix is the input here and is not rebuilt. What is new is everything done with it — the diagonal gives a fault current, the column gives a voltage profile and a set of line currents, a modification gives the fault level after a new machine is commissioned, and a tap on a line gives the current for a fault that is nowhere near a bus.
The second half converts current into hardware. A breaker meets the fault twice, at two instants that need two different networks, and the standards handle the decay of the machine flux by de-rating the motors rather than by solving anything. The last three problems end where every real study ends: at a catalogue page, with every row of a nameplate checked and a margin quoted.
The diagonal is a Thévenin impedance. \(Z_{kk}\) is what the network presents at bus \(k\) with every source shorted, so a bolted three-phase fault there draws \(I_f = V_f/Z_{kk}\). Nothing else in the matrix is needed for the current itself.
The column is the rest of the study. Injecting \(-I_f\) at bus \(k\) changes bus \(i\) by \(-Z_{ik}I_f\), so \(V_i = V_f\!\left(1 - Z_{ik}/Z_{kk}\right)\) and every line current follows by Ohm's law. One column answers one fault location completely.
Fault level and impedance are one statement. \(S_{sc} = \mathrm{MVA}_{base}/|Z_{kk}|_{pu}\), exactly, because the prefault profile is flat at \(1.0\). A declared fault level is therefore a complete positive-sequence model of everything behind the supply point: \(X_{source} = \mathrm{MVA}_{base}/S_{sc}\).
A breaker meets the fault twice. Half a cycle after inception it may have to close onto it and latch; three or four cycles later it must part its contacts and interrupt. Two instants, two networks of identical topology, two different sets of machine reactances.
Motors are sources, and they decay. In the first-cycle network a large motor stands at \(1.0X''_d\); in the interrupting network at \(1.5X''_d\), and small induction motors at \(3.0X''_d\) or are dropped altogether. Generators are unchanged, because their flux decays slowly.
The duties by the \(E/X\) method. \(I_{mom,rms} = 1.6E/X_{first}\) and \(i_{mom,crest} = 2.7E/X_{first}\); \(I_{int} = \mathrm{MF}\times E/X_{int}\), with \(\mathrm{MF}=1.0\) for a remotely fed fault and 1.1–1.3 close to generation.
Making current is not an independent rating. IEC fixes \(i_p = 2.5I_{sc}\) at 50 Hz and \(2.6I_{sc}\) at 60 Hz — the breaking current re-expressed as the crest of a fully offset wave. A breaker can therefore pass the breaking check and fail the making check, and Problem 14 is that case.
Series reactance is the only lever. A reactor, a bus split or a high-impedance transformer all buy fault-level headroom with the same currency, and all three are paid for in regulation, in losses and in the \(P_{max}=|E||V|/X\) of Part 6.
A 132 kV bus in a network studied on a 100 MVA base has \(Z_{kk}^{(1)} = j0.125\) per unit. Find the bolted three-phase fault current in per unit and in kA, and the fault level in MVA. Then invert the question: a utility declares a fault level of 2500 MVA at another 132 kV point — what is the Thévenin impedance there, in per unit on the same base and in ohms?
The current in per unit. With the prefault profile flat at \(V_f = 1.0\angle0^\circ\) and the fault bolted, the diagonal entry is the whole calculation:
The current lags the prefault voltage by \(90^\circ\) because resistance was neglected. Only its magnitude, 8.000 pu, matters for a rating.
The base current at 132 kV, which is the only conversion needed:
Three and a half kiloamps. Note that this is a line current, because the per-unit system was set up on three-phase MVA and line-to-line kV, so no \(\sqrt3\) appears anywhere in the conversion.
The fault level, which is the same fact expressed as apparent power:
The two routes agree exactly, and they must: the reciprocal relation between per-unit impedance and fault MVA is an identity when \(V_f = 1.0\), not an approximation.
The inverse question. A declared fault level is a complete positive-sequence model of everything upstream. Converting it to the study base is one division:
Seven ohms per phase, referred to 132 kV, replaces however many hundred kilometres of network and however many machines lie behind that point. That single number is what a utility hands to a consultant, and it is all the consultant needs.
The direction of the inequality is worth fixing in the mind. A low Thévenin impedance is a high fault level and a strong bus; a high impedance is a weak bus with a small fault current. The 2500 MVA point is three times stiffer than the 800 MVA one, so its impedance is a third as large.
A 50 MVA, 132/33 kV transformer of 12.5% reactance feeds a 33 kV switchboard. The utility declares a fault level of 3500 MVA at the 132 kV supply point. Find the fault level and symmetrical fault current at the 33 kV bus and the peak making current a 50 Hz breaker there must provide. Then state, as a percentage, the error made by treating the 132 kV supply as an infinite bus.
Put both impedances on a 100 MVA base. The utility becomes a reactance from the reference to the 132 kV point; the transformer needs the ordinary base change of Set 3:
The transformer's percentage reactance is on its own 50 MVA rating, so it doubles when carried to a 100 MVA base. The utility's figure needed no rating at all — a fault level already carries its own.
The two are in series, because the only path from the reference to the 33 kV bus runs through both:
Fault level and current at 33 kV:
Check by the other route: \(358.97/(\sqrt3\times33) = 6.280\) kA. The two agree.
The peak making current, at the IEC 50 Hz ratio of Section 25-7:
A 36 kV, 25 kA breaker with a 62.5 kA peak making rating clears both duties with a very large margin — the 33 kV board here is a weak one, fed through a single transformer.
The infinite-bus error. Dropping \(X_{source}\) leaves the transformer alone:
The source reactance is only 11.4% of the transformer's, and it inflates the answer by exactly 11.4% — the two percentages coincide here because fault current depends on the reciprocal of a sum, so a small addition to the denominator produces a proportionally equal reduction in the result.
When the error stops being small. Repeat with a weaker utility, say 800 MVA, and \(X_{source}=0.125\) against the transformer's 0.250. Now \(X_{th}=0.375\), \(S_{sc}=266.7\) MVA, and the infinite-bus assumption overstates the fault level by 50%. The error equals the ratio of source reactance to transformer reactance, so it is negligible for a stiff grid and inadmissible for a weak one.
The five-bus 132 kV network built element by element in Set 18 has, on a 100 MVA base,
Tabulate the bolted three-phase fault current in per unit and in kA and the fault level at every bus, rank the buses, and say whether the ranking could have been guessed from the single-line diagram.
The network. Two machines, seven lines, all reactances in per unit on 100 MVA. Bus 2 is the hub, with four connections; bus 5 hangs off it and off bus 4.
The base current, the same for every bus because the whole network is at 132 kV:
Read the diagonal and divide. Each row of the table below is \(1/Z_{kk}\), then multiplied by \(I_{base}\), then \(100/Z_{kk}\):
| Bus | \(Z_{kk}\) pu | \(I_f\) pu | \(I_f\) kA | \(S_{sc}\) MVA | Rank |
|---|---|---|---|---|---|
| 1 | \(j0.12514\) | 7.991 | 3.495 | 799.1 | 2 |
| 2 | \(j0.12009\) | 8.327 | 3.642 | 832.7 | 1 (strongest) |
| 3 | \(j0.17377\) | 5.755 | 2.517 | 575.5 | 3 |
| 4 | \(j0.17680\) | 5.656 | 2.474 | 565.6 | 4 |
| 5 | \(j0.20457\) | 4.888 | 2.138 | 488.8 | 5 (weakest) |
The whole table is one column of arithmetic. No network reduction was performed, and none is needed: the matrix was built once, in Set 18, and answers all five questions at once.
Yes, the ranking is readable from the diagram, and checking that it is readable is the first sanity test on any completed matrix:
Buses 3 and 4 differ by 1.7% in fault level because the \(j0.03\) tie between them is an order of magnitude stiffer than anything else touching them. A matrix that ranked them differently, or ranked bus 5 above bus 3, would be evidence of an arithmetic error somewhere in the build.
The spread is only 1.7 to 1. From 833 MVA at the strongest bus to 489 MVA at the weakest — a small range, because both machines are electrically close to every bus in a network this compact. In a long radial system the ratio between the strongest and weakest bus is commonly ten to one, and the switchgear specification differs accordingly from one end to the other.
A bolted three-phase fault occurs at bus 5 of the network of Problem 3. Using column 5 of the matrix only, find the voltage at every bus during the fault, express each as a percentage sag, and identify which bus a plant undervoltage relay set at 0.45 pu would see as healthy.
The fault current first, from the diagonal:
The superposition statement. Before the fault every bus stands at \(V_f = 1.0\). The fault is an injection of \(-I_f\) at bus 5, and a single injection at bus \(k\) changes bus \(i\) by \(-Z_{ik}I_f\):
The fault current cancels out of the ratio, so the voltage profile depends only on the shape of the column, not on its scale. That is why the same profile is obtained whether the prefault voltage is taken as 1.00 or 1.05 pu.
One division per bus, using column 5 \((0.10160,\ 0.11872,\ 0.13064,\ 0.13626,\ 0.20457)\) over \(Z_{55}=0.20457\):
| Bus \(i\) | \(Z_{i5}\) | \(Z_{i5}/Z_{55}\) | \(V_i\) pu | Sag |
|---|---|---|---|---|
| 1 | 0.10160 | 0.4967 | 0.5034 | 49.7% |
| 2 | 0.11872 | 0.5804 | 0.4196 | 58.0% |
| 3 | 0.13064 | 0.6386 | 0.3614 | 63.9% |
| 4 | 0.13626 | 0.6661 | 0.3339 | 66.6% |
| 5 | 0.20457 | 1.0000 | 0.0000 | 100% |
The relay question. With a pickup at 0.45 pu, only bus 1 at 0.503 pu stays above the setting:
So an undervoltage element at bus 1 does not pick up while three other substations are in a deep sag. That is the mechanism behind a familiar complaint: a fault at one end of a system trips motor contactors at the far end and not at the near one, because electrical distance is not geographical distance.
The ordering is not the ordering of the diagram. Bus 4 sags more deeply than bus 2, although bus 2 is joined to bus 5 by the stiffest of the two paths (\(j0.12\) against \(j0.24\)). The reason is that bus 2 has a machine on it holding it up, and bus 4 has none:
The ratio is a dimensionless distribution factor. It is 1 at the fault itself and would be 0 at a bus completely disconnected from the fault — for example, at any bus on the far side of a delta winding in the zero-sequence network of Set 22.
A check that costs nothing. Every voltage must lie between 0 and \(V_f\), and the faulted bus must come out at exactly zero. Setting \(i=k=5\) gives \(1 - Z_{55}/Z_{55} = 0\) identically, which confirms that the right column was used.
For the same fault at bus 5, find the current in every line of the network in per unit and in kA, and verify the result at the fault point. The line reactances are 1–2 \(j0.06\), 1–3 \(j0.24\), 2–3 \(j0.18\), 2–4 \(j0.18\), 2–5 \(j0.12\), 3–4 \(j0.03\), 4–5 \(j0.24\). Which breaker in the network carries the largest current, and is it the one at the faulted bus?
Ohm's law on each branch, using the voltages of Problem 4:
The bus voltages are the only thing the matrix was needed for. Once they exist, the branch currents are elementary — and this is the reason the whole study is arranged around \(\mathbf{Z}_{\text{bus}}\) rather than around any direct current calculation.
Line 1–2, worked in full as the pattern for the rest:
Positive in the direction 1 to 2, so current flows from bus 1 towards bus 2 — from the machine that is holding its voltage up, towards the fault.
All seven branches, with the kA column at \(I_{base}=0.43739\) kA:
| Line | \(V_i - V_j\) | \(z_{ij}\) | \(|I_{ij}|\) pu | kA |
|---|---|---|---|---|
| 1–2 | 0.08371 | \(j0.06\) | 1.3951 | 0.610 |
| 1–3 | 0.14196 | \(j0.24\) | 0.5915 | 0.259 |
| 2–3 | 0.05826 | \(j0.18\) | 0.3237 | 0.142 |
| 2–4 | 0.08571 | \(j0.18\) | 0.4762 | 0.208 |
| 2–5 | 0.41964 | \(j0.12\) | 3.4970 | 1.530 |
| 3–4 | 0.02746 | \(j0.03\) | 0.9152 | 0.400 |
| 4–5 | 0.33393 | \(j0.24\) | 1.3914 | 0.609 |
The verification at the fault point. Only two lines enter bus 5, and everything that arrives must go into the fault:
Agreement to five figures. This check is worth doing every time, because it tests the voltage profile, the line data and the diagonal entry simultaneously; a transposed matrix element or a mis-keyed reactance will fail it immediately.
A second check at an unfaulted bus. Kirchhoff's current law must also hold at bus 3, which has no machine and no fault, so its three branch currents must sum to zero:
Which breaker carries the most. The largest branch current is 3.497 pu, or 1.530 kA, in line 2–5:
No breaker in the network interrupts 4.888 pu. The fault current is shared, and each breaker's duty is its own branch current — which for the bus-5 fault is at most 72% of the total. Rating every breaker at a bus for the full bus fault level is conservative and is what is actually done for busbar switchgear, but for a line breaker it can be a substantial over-specification.
Split the bus-5 fault current of Problem 4 between the two generators, by two independent methods, and state what fraction of its own rating each machine is delivering. \(G_1\) is a 50 MVA unit with \(x''_d = 0.125\) on its own rating and \(G_2\) is a 60 MVA unit with \(x''_d = 0.12\); each is the shunt branch at its own bus.
Confirm the machine branches first. On the 100 MVA base:
Which are the two shunt branches used in Set 18's build — \(j0.25\) at bus 1 and \(j0.20\) at bus 2. The data is consistent, and that consistency is worth checking before any current is computed.
Method one: current out of each machine branch. Each generator is an emf of 1.0 pu behind its own reactance, and the bus it stands on has fallen to the value found in Problem 4:
Method two: the branch currents leaving each generator's bus. Everything \(G_1\) produces must leave bus 1 along its two lines, and everything \(G_2\) produces must be the net outflow at bus 2:
Note the sign on \(I_{12}\): line 1–2 brings current into bus 2, so it is subtracted from what leaves. Two entirely different routes through the arithmetic give the same two numbers, which is as strong a check as a hand calculation admits.
The shares:
The smaller-reactance machine at the better-connected bus supplies more, as it must. \(G_2\) reaches bus 5 through \(j0.12\) directly; \(G_1\) reaches it only through bus 2 or the long way round through buses 3 and 4.
In terms of each machine's own rating. Convert to the machine base by the ratio of ratings:
Four to five times full load, which is what \(1/x''_d\) of 8 and 8.33 would give for a fault at the machine's own terminals, reduced by the network between. Both figures are within the short-circuit withstand of a normally specified machine, and both are far above anything the stator could carry for more than a few seconds.
An observation the ratings make possible. \(G_2\) is 20% larger than \(G_1\) but delivers 46% more fault current. Fault contribution scales as \(\mathrm{MVA}/x''_d\) and not as MVA, so a machine with a low subtransient reactance is a disproportionately large contributor. That is a purchasing decision: specifying \(x''_d\) a few per cent higher costs a little efficiency and buys fault-level headroom for the life of the plant.
A three-phase fault at bus 4 of the network of Problem 3 is not bolted: an arcing path of \(Z_f = j0.05\) per unit stands between the three phases and the point of contact. Find the fault current, the voltage at the fault point itself, and the voltage profile. By what percentage does the fault impedance reduce the current, and why is the reduction so much larger than the 5% the number might suggest?
The fault impedance is in series with the Thévenin impedance, because the whole network reduces to one branch at the fault point:
The bolted case for comparison, from Problem 3:
A fault impedance of 0.05 pu — five per cent of one — cuts the current by 22%. The arithmetic is not subtle: 0.05 is not 5% of anything relevant, it is 28% of \(Z_{44}\), and it is the ratio to \(Z_{44}\) that matters.
The general statement. Write \(\lambda = Z_f/Z_{kk}\):
A reduction of 22.05%, matching the direct calculation. The lesson generalises: at a strong bus, where \(Z_{kk}\) is small, a given arc impedance matters more, not less. A 0.05 pu arc at bus 2 (\(Z_{22}=0.12009\)) would remove 29% of the current.
The faulted bus is no longer at zero volts. The fault impedance carries the whole fault current:
Twenty-two per cent of nominal remains at the fault point — nearly 17 kV of arc voltage on a 132 kV system. A disturbance recorder that shows a residual voltage at the fault point is showing an arcing fault, and the recorded value is the direct measurement of \(Z_f I_f\).
The rest of the profile, from \(V_i = 1 - Z_{i4}/(Z_{44}+Z_f)\) with column 4:
| Bus | \(Z_{i4}\) | \(V_i\), bolted | \(V_i\), \(Z_f=j0.05\) |
|---|---|---|---|
| 1 | 0.10502 | 0.4060 | 0.5369 |
| 2 | 0.11598 | 0.3440 | 0.4886 |
| 3 | 0.16201 | 0.0836 | 0.2857 |
| 4 | 0.17680 | 0.0000 | 0.2205 |
| 5 | 0.13626 | 0.2293 | 0.3992 |
Every voltage is lifted, and by more at the buses nearest the fault. Bus 3, which sits behind the stiff \(j0.03\) tie to bus 4, rises from 0.084 to 0.286 pu — the sag it suffers is very nearly the sag at the fault, arc or no arc.
Why rating calculations still assume a bolted fault. Every effect of \(Z_f\) is to reduce the current, so the bolted assumption is the conservative one and no argument about the arc's resistance can invalidate a rating based on it. The arc matters in the other direction — for protection, where an underestimate of the fault current can leave a relay short of pickup, and for arc-flash energy, where the arc voltage is precisely the term that makes the incident energy nonzero.
A fault occurs 40% of the way along line 2–4 (total reactance \(j0.18\)), measured from bus 2. Using the building algorithm of Set 18 on the existing five-bus matrix, find the Thévenin impedance at the fault point and the fault current. Then sweep the fault along the whole line and locate the point of minimum fault current — which is not, as intuition suggests, at either end.
The tap point is a new bus. A fault at a point \(p\) that is not a bus is handled by making it one: line 2–4 is deleted and replaced by two sections in series through \(p\). Three modifications are needed, in this order:
Removing an element is adding one of negative impedance — the same Type 4 formula with the sign reversed. That is the whole trick, and it is why the building algorithm is worth having in a planning study where lines come and go.
Step A, removing line 2–4. The fictitious diagonal is
Negative, as it must be when an element is deleted; the network's own impedance between buses 2 and 4 is \(j0.06493\), smaller than the line being removed, so the removal will raise every diagonal.
The matrix with line 2–4 out:
Bus 4 is worst hit: \(Z_{44}\) rises 18%, from \(j0.17680\) to \(j0.20895\), because it has lost one of its three connections. Bus 1 barely moves.
Step B, the tap bus. A Type 2 addition from bus 2 to the new bus \(p\): the new row and column copy row and column 2, and
At this stage \(p\) is a dead end fed only from bus 2, so its Thévenin impedance is bus 2's plus the section — exactly what a first-year calculation would give.
Step C, closing the loop to bus 4:
The correction term uses \(Z_{pp}-Z_{p4}=j0.07843\), the difference between the two ends of the closing branch. Squared and divided by \(Z_{ll}\), it removes 11% of the tap bus's impedance.
The fault at the 40% point:
An independent check: rebuilding a six-bus \(\mathbf{Y}_{\text{bus}}\) with the split line and inverting it gives \(Z_{pp}=j0.170393\), agreeing to six figures.
Now sweep the fault along the line. Repeating the three steps with \(\alpha\) in place of 0.4:
| \(\alpha\) from bus 2 | \(Z_{pp}\) pu | \(I_f\) pu | \(I_f\) kA |
|---|---|---|---|
| 0 (at bus 2) | \(j0.12009\) | 8.327 | 3.642 |
| 0.25 | \(j0.15584\) | 6.417 | 2.807 |
| 0.40 | \(j0.17039\) | 5.869 | 2.567 |
| 0.50 | \(j0.17721\) | 5.643 | 2.468 |
| 0.746 | \(j0.18420\) | 5.429 | 2.375 |
| 1 (at bus 4) | \(j0.17680\) | 5.656 | 2.474 |
Why the minimum is inside the line. Bus 4 is not a dead end: it is tied to bus 3 by \(j0.03\) and to bus 5 by \(j0.24\), so the network reaches the fault from both ends of line 2–4. Moving the fault away from bus 2 raises the impedance of one path and lowers the other, and the sum is maximised where the two are comparable:
A parabola-like curve with an interior maximum. It degenerates to a monotonic rise only when the far end is a dead end, \(Z_B\to\infty\) — which is the radial case every student pictures.
What it costs to get this wrong. Assuming the far bus gives the smallest current would predict 2.474 kA as the minimum; the true minimum is 2.375 kA, 4.0% lower. An earth-fault or overcurrent relay graded on the larger figure is 4% short of where it thinks it is — small here, but on a long line fed strongly from both ends the discrepancy reaches 15 to 20% and decides whether the far end of a line is covered at all.
The fault current a breaker actually meets is not the phasor a fault study produces. Starting from the transient of Set 32, derive the rms and crest asymmetry factors half a cycle after inception for a fully offset wave, evaluate them at \(X/R = 15\), 20 and 30, and say why the ANSI figures 1.6 and 2.7 are the ones quoted.
The current after inception, for a fault applied at the instant that produces full offset:
Two terms: a decaying unidirectional component whose initial value equals the crest of the AC term, and the AC term itself. The DC term exists because the current in an inductive circuit cannot jump, so a component must be added to make \(i(0)=0\).
The decay in cycles. One cycle is \(t = 2\pi/\omega\), so
The decay depends on \(X/R\) alone, not on the impedance magnitude — which is why \(X/R\) is the one extra number a fault study must carry beyond the reactances.
The two factors. Half a cycle after inception the AC term is again at its crest and the DC term has decayed by \(e^{-\pi R/X}\). The crest of the total is the sum, and the rms of an AC component plus a DC component is the root of the sum of squares:
The 2 inside the root is \((\sqrt2)^2\): the DC component's contribution to the rms is its own instantaneous value squared, and that value is \(\sqrt2\) times the rms of the AC part.
Evaluated:
| \(X/R\) | \(e^{-\pi R/X}\) | \(k_{rms}\) | \(k_{crest}\) | Where met |
|---|---|---|---|---|
| 10 | 0.7304 | 1.438 | 2.447 | Distribution, cable-fed |
| 15 | 0.8110 | 1.522 | 2.561 | Industrial board |
| 20 | 0.8546 | 1.569 | 2.623 | Transformer-fed HV bus |
| 30 | 0.9006 | 1.619 | 2.688 | Generator terminals |
| \(\infty\) | 1 | 1.732 | 2.828 | Lossless limit |
Why 1.6 and 2.7. The ANSI figures are the values at \(X/R \approx 30\), rounded down slightly:
Thirty is the ratio near large generation, which is where the momentary duty is most severe. Applying the same 1.6 at an industrial board with \(X/R=15\) overstates the duty by 5%, which is accepted as the price of having one number instead of a table.
The lossless limit is worth knowing, because it bounds everything: as \(R\to0\) nothing decays, \(k_{crest}\to2\sqrt2 = 2.828\) and \(k_{rms}\to\sqrt3 = 1.732\). No breaker anywhere ever meets more than 2.83 times the symmetrical rms current as a crest, and the IEC making-current ratio of 2.5 sits comfortably below that because a real circuit has resistance and a real closing takes finite time.
An 11 kV plant bus is supplied by a utility whose fault level there is 300 MVA and by a 12.5 MVA local generator with \(X''_d = 0.16\). Connected to the same bus are a 5 MVA synchronous motor with \(X''_d = 0.20\), a group of induction motors above 1000 hp totalling 7 MVA with \(X''_d = 0.17\), and a group of smaller induction motors, all above 50 hp, totalling 4 MVA with \(X''_d = 0.17\). On a 100 MVA base, build the first-cycle and interrupting networks and find \(X_{first}\) and \(X_{int}\).
Every branch on the 100 MVA base. The utility from its declared fault level, the machines by the ratio of ratings:
All five stand between the bus and the reference, so the network is five branches in parallel and nothing else. The topology is identical in both cases; only the values change.
The de-rating factors, from the ANSI table of Section 25-6:
The generator is untouched between the two networks because its field circuit keeps it excited; a motor loses its excitation the moment the bus voltage collapses, and the smaller its rotor time constant the faster its contribution dies.
The first-cycle network, five parallel admittances:
Only the small induction motors are altered here, from 4.25 to \(1.2\times4.25=5.10\). Working in admittances rather than impedances is not a convenience but a necessity — parallel branches add only in that form, and the sum is also the fault current in per unit.
The interrupting network, with three of the five branches enlarged:
What has actually changed. The two non-motor branches contribute 3.78125 in both networks; the three motor branches fall from 0.85784 to 0.51961, a loss of 39.4% of the motor contribution:
Under 8% change in the network impedance, because the motors were never the dominant branch here. In a plant fed by a weak utility with a large motor load the same calculation can move \(X\) by 30%.
A structural point about the method. Nothing has been integrated, no time constant has been used, and no differential equation has been solved. The standards replace a continuously decaying source by two frozen snapshots taken at the two instants the hardware cares about, and the whole of the machine physics has been reduced to a column of multipliers.
From the two networks of Problem 10, compute the symmetrical first-cycle current, the momentary rms and crest duties, and the interrupting duty in kA, taking \(\mathrm{MF} = 1.0\). Then repeat the interrupting duty with \(\mathrm{MF} = 1.1\) and say what physical situation would require it.
The base current at 11 kV:
Large, because 11 kV is a low voltage to move 100 MVA through. That is the reason industrial switchgear carries the biggest fault currents in a power system while the transmission network carries the biggest fault MVA.
The symmetrical currents. With \(E = V_f = 1.0\), the per-unit current is simply the admittance sum already formed:
The momentary duties, at the ANSI factors of Problem 9:
The crest figure is the one checked against a breaker's rated short-circuit making current, and it is also the number the busbar bracing is designed to, since the force between conductors goes as the square of the instantaneous current.
The interrupting duty:
\(\mathrm{MF}=1.0\) is justified here because two thirds of the current arrives from the utility through transformers and cable, so the composite \(X/R\) at the bus is well below 17 and the DC offset has essentially gone by the time the contacts part.
With \(\mathrm{MF}=1.1\):
Two situations force this. The first is a fault fed predominantly from local generation, where \(X/R\) reaches 30 and the offset survives; the second is a fast breaker, whose contacts part in two cycles rather than four and therefore meet a current that has had less time to decay. Both are cases where the DC component has not finished dying, and MF is the factor that accounts for it.
Collecting the three numbers a purchase specification needs:
Note that the largest of the three is a peak and the other two are rms, so they cannot be compared with one another. Problem 14 checks each against its own nameplate row.
For the plant bus of Problem 10, tabulate each source's contribution to the first-cycle and interrupting currents in kA and as a percentage. State what the motors are worth in each network, how much of their contribution has decayed, and what a study that treated the motors as passive load would have reported.
Each branch is its own current source. With all internal emfs equal to \(V_f\) and every branch running straight from the bus to the reference, no divider algebra is needed — each contribution is the reciprocal of its own reactance:
The two tables, at \(I_{base}=5.2486\) kA:
| Source | First cycle, kA | Share | Interrupting, kA | Share |
|---|---|---|---|---|
| Utility, 300 MVA | 15.746 | 64.7% | 15.746 | 69.8% |
| Generator, 12.5 MVA | 4.100 | 16.8% | 4.100 | 18.2% |
| Synchronous motor, 5 MVA | 1.312 | 5.4% | 0.875 | 3.9% |
| Induction motors \(>\)1000 hp, 7 MVA | 2.161 | 8.9% | 1.441 | 6.4% |
| Induction motors \(\ge\)50 hp, 4 MVA | 1.029 | 4.2% | 0.412 | 1.8% |
| Total | 24.349 | 100% | 22.574 | 100% |
Each column sums to the totals of Problem 11, which is the check: the sum of the reciprocals of the branch reactances must equal the reciprocal of the parallel combination.
What the motors are worth:
Two fifths of the motor contribution has gone in three cycles, and the loss is very unevenly distributed: the small induction motors lose 60% of theirs, the large ones and the synchronous machine a third.
The study that treated motors as load. Delete all three motor branches:
The momentary crest would come out at \(2.7\times19.85 = 53.6\) kA instead of 65.7 kA — and Problem 14 will show that the difference between those two figures is exactly the difference between a breaker that is adequate and one that is not.
Why the error is worse in the first cycle than at interruption. Because the motors decay and the utility does not, the motor share falls from 18.5% to 12.1%. Neglecting motors therefore does the most damage to the making and bracing checks, which are the ones least often revisited. A plant that grows by adding motors moves its momentary duty faster than its interrupting duty, and can outgrow its switchgear's close-and-latch rating while still comfortably inside its breaking rating.
A rule of thumb worth carrying. An induction motor contributes roughly \(1/X''_d \approx 5\) to 6 times its own rated current for the first few cycles. A plant with 16 MVA of motors on a bus fed by 300 MVA of utility therefore adds about \(16\times5.5 = 88\) MVA of first-cycle contribution — 29% on top of the utility — which is the order of the 22.7% found above.
A 12 kV breaker is rated 25 kA symmetrical short-circuit breaking current. Find its rated making current at 50 Hz and at 60 Hz and its breaking capacity in MVA. Show that the IEC factors 2.5 and 2.6 follow from a standard DC time constant of 45 ms, and state the breaking current a duty of 65.74 kA peak would demand.
Making current is not an independent rating. It is the breaking current re-expressed as the crest of a fully offset wave:
Where 2.5 and 2.6 come from. IEC 62271-100 fixes the DC time constant of the test circuit at \(T = 45\) ms for both frequencies, so the difference is entirely in the length of the half cycle:
The 60 Hz crest arrives sooner, so less of the offset has died. A 45 ms time constant corresponds to \(X/R = 2\pi f T = 14.1\) at 50 Hz — a deliberately moderate figure, which is why installations near large generation are given a separate, higher-offset test duty.
Breaking capacity in MVA, the older way of quoting the same rating:
Note the rated voltage, 12 kV, not the nominal system voltage of 11 kV. Using 11 kV would understate the capacity by 8.3% and is the commonest slip in this calculation.
The reverse question. A study demanding a 65.74 kA peak — the momentary duty of Problem 11 — implies a breaking rating of at least
Which is more than 25 kA. The 25 kA breaker fails the making check although its breaking rating exceeds the 22.57 kA interrupting duty by 11%. The two checks use different currents — the first-cycle current and the interrupting current — so passing one does not imply passing the other, and the making check is the one more often binding in plants with heavy motor load.
A short comparison across the standard classes, to fix the orders of magnitude:
| Class | \(I_{sc}\) | \(i_p\) at 50 Hz | Breaking capacity |
|---|---|---|---|
| 12 kV | 25 kA | 62.5 kA | 520 MVA |
| 12 kV | 31.5 kA | 78.8 kA | 655 MVA |
| 36 kV | 25 kA | 62.5 kA | 1559 MVA |
| 145 kV | 31.5 kA | 78.8 kA | 7911 MVA |
| 420 kV | 63 kA | 157.5 kA | 45830 MVA |
The current rises by a factor of only 2.5 from the smallest to the largest entry while the capacity rises by a factor of 88 — because capacity carries the voltage. That is why a 12 kV interrupter is a small device handling a large current and a 420 kV one is a large device handling a moderate one.
Select a breaker for the 11 kV plant bus of Problems 10 to 12. The duties are 24.35 kA symmetrical first cycle, 65.74 kA peak momentary and 22.57 kA interrupting; the continuous load is 1250 A; backup protection clears in 0.8 s. The 12 kV class offers 25, 31.5 and 40 kA breaking with making currents of 62.5, 78.8 and 100 kA peak and 3 s short-time ratings equal to the breaking current. Check every row of the nameplate and quote the smallest margin on the unit chosen.
Rated voltage first, because it is a yes-or-no test and disposes of nothing else. The system's highest voltage is 12 kV against a nominal 11 kV, so the 12 kV class is correct; a 7.2 kV unit is inadmissible whatever its current rating.
Rated normal current. The 1250 A load is a continuous thermal duty unrelated to the fault:
Standard values run 630, 1250, 1600, 2000, 2500, 3150 A. Choosing 1250 A exactly leaves no room for emergency transfers, which are the reason a bus-section breaker in a two-incomer board must carry the whole board.
The 25 kA candidate, checked row by row:
| Rating | Nameplate | Duty | Margin |
|---|---|---|---|
| Short-circuit breaking | 25 kA rms | 22.57 kA | +10.8% ✓ |
| Short-circuit making | 62.5 kA peak | 65.74 kA | −4.9% ✗ |
| Short-time withstand | 25 kA, 3 s | 22.57 kA, 0.8 s | ample ✓ |
Rejected on the making current. The breaking rating is adequate; the close-and-latch rating is not. That is the case Problem 13 anticipated, and it happens because the first-cycle current is 8% larger than the interrupting current while the two nameplate figures are tied together by the fixed ratio 2.5.
The 31.5 kA candidate:
| Rating | Nameplate | Duty | Margin |
|---|---|---|---|
| Rated voltage | 12 kV | 11 kV nominal, 12 kV max | ✓ |
| Rated normal current | 1600 A | 1250 A | +28% ✓ |
| Short-circuit breaking | 31.5 kA rms | 22.57 kA | +39.6% ✓ |
| Short-circuit making | 78.8 kA peak | 65.74 kA | +19.9% ✓ |
| Short-time withstand | 31.5 kA, 3 s | 22.57 kA, 0.8 s | +630% on \(I^2t\) ✓ |
The thermal row in figures, since "ample" is not an engineering statement:
Why not go straight to 40 kA. Its margins are 77% and 52%, and margins that large are not free: a 40 kA cubicle is physically larger, its busbar bracing is heavier, and the whole switchboard grows. Fifteen to twenty per cent is the accepted band, and 19.9% sits at the top of it — which is right for a plant likely to add motor load.
What the choice would have been on a careless study. Problem 12 showed that neglecting the motors gives 19.85 kA first cycle and a crest duty of \(2.7\times19.85 = 53.6\) kA. Against a 62.5 kA making rating that is a 17% margin, and the 25 kA breaker would have been bought. The motors are the difference between the right answer and a switchboard that cannot survive a reclosure onto a standing fault.
An older breaker is offered on the ANSI total-current basis: rated maximum voltage 15 kV, rated short-circuit current 18 kA at that voltage, voltage range factor \(K = 1.3\). Find its interrupting capability at 11 kV, the voltage below which the capability stops rising, and whether it would serve the 22.57 kA duty of Problem 11.
What the factor means. Used below its rated maximum voltage, such a breaker can interrupt more, because the recovery voltage across the gap is lower — but not without limit, since beyond some point the mechanism rather than the dielectric becomes the constraint:
The two candidates at 11 kV:
The \(K\) ceiling governs. Taking the inverse-voltage figure alone would credit the breaker with 1.15 kA it does not have.
The transition voltage, where the two expressions cross:
Above 11.54 kV the capability rises inversely with voltage; below it, the capability is flat at 23.40 kA however far the voltage falls. An 11 kV system sits just inside the flat region — which is why the 15 kV class was built with \(K=1.3\) in the first place.
Against the duty:
It passes, and only just. Three and a half per cent of margin is inside the uncertainty of the study itself — the prefault voltage was taken at 1.00 rather than 1.05 pu, and at 1.05 pu the duty is \(1.05\times22.57 = 23.70\) kA, which the breaker would fail. The unit is not acceptable for this bus.
Modern practice has removed the factor. IEC declares one symmetrical breaking current valid across the whole rated voltage range, with the permitted DC component at contact separation stated separately. The engineering is unchanged; only the bookkeeping differs — and a specification written against one standard must be translated before it is compared with a study run against the other.
A 12 kV breaker is rated 25 kA for 3 s. The board it protects has a symmetrical fault duty of 22.6 kA with \(X/R = 15\); main protection clears in 0.35 s and breaker-failure backup in 1.2 s.
- Find the permissible duration at 22.6 kA and check both clearing times.
- Include the DC component in the heating, and find the thermally equivalent rms current for each clearing time.
- A colleague proposes reading the rating "the other way" — 43.3 kA for 1 s. Show why this is inadmissible.
The rating is an energy, not a current. Adiabatic heating over a short fault makes the temperature rise proportional to \(\int i^2\,dt\), so the nameplate pair \(I_k / t_k\) is shorthand for
Both clearing times pass on this basis: 0.35 s and 1.2 s are well inside 3.671 s. The backup time is the one that matters, because it is the duration the breaker must survive while a different breaker fails to clear.
Part 2 — the DC component adds heat. With a fully offset wave the current is \(i = \sqrt2 I\big[e^{-t/T} - \cos\omega t\big]\). Integrating the square over \([0,t]\) and averaging out the cross term, the AC part contributes \(I^2t\) and the DC part
The DC time constant at \(X/R = 15\):
Over 0.35 s the exponential has long since vanished, so \(1-e^{-2t/T}\to1\) and \(m\) reduces to \(T/t\).
The equivalent currents:
Both far below 1875. Note that the DC contributes proportionally more for a fast clearance, because the offset's energy is a fixed quantity delivered in the first 50 ms whatever happens afterwards — so a 6.6% uplift at 0.35 s becomes only 2.0% at 1.2 s. For clearances of a few cycles, which is where a differential scheme operates, the uplift reaches 30 to 50% and cannot be ignored.
Part 3 — why the rating cannot be traded upward. The proposal is
Thermally the arithmetic is sound: 1875 kA²s either way. Electrically it is nonsense, because a 43.3 kA symmetrical fault brings with it a peak of
The contacts would be blown apart by the electromagnetic force long before the heating became the issue. The short-time withstand may be traded from \(t_k\) to longer durations at lower current, but never to shorter durations at higher current, because the peak withstand caps it. IEC states the limit explicitly: the rating is valid for durations up to \(t_k\), and the current is never to exceed the rated short-circuit breaking current.
The same rule applies to everything else in the circuit. A current transformer, a cable and a busbar all carry \(I^2t\) ratings, and all three are checked against the backup clearing time, not the main one:
With \(k=94\) for XLPE-insulated copper, a 22.6 kA fault held for 1.2 s needs \(22600\sqrt{1.2}/94 = 263\ \text{mm}^2\) of copper. The breaker was never the binding constraint; the cable is.
A 60 MVA generating unit with \(x''_d = 0.18\) on its own rating is to be connected at bus 5 of the five-bus network of Problem 3. Modify \(\mathbf{Z}_{\text{bus}}\) by the building algorithm rather than re-inverting, tabulate the new fault level at every bus, and identify which existing switchgear is put at risk if the busbars were originally rated 1000 MVA.
The new branch on the study base:
A shunt from an existing bus to the reference — a Type 3 addition, which closes a loop and therefore changes every element of the matrix.
The Type 3 modification, a single rank-one correction using column 5:
One denominator for the whole matrix, and the numerator is the outer product of column 5 with itself. That is the entire cost of adding a machine — no inversion, and the arithmetic is the same for a five-bus network as for a five-thousand-bus one, per column.
The five diagonals, worked:
The independent check at bus 5, where the modification is a simple parallel combination:
Exact agreement. The check works only at the bus the element was added to, and it is worth doing every time, because it catches a wrong column or a wrong denominator immediately.
The consequences, bus by bus:
| Bus | \(S_{sc}\) before | \(S_{sc}\) after | Rise | \(I_f\) after, kA |
|---|---|---|---|---|
| 1 | 799.1 | 955.2 | +19.5% | 4.178 |
| 2 | 832.7 | 1085.1 | +30.3% | 4.746 |
| 3 | 575.5 | 714.5 | +24.2% | 3.125 |
| 4 | 565.6 | 714.2 | +26.3% | 3.124 |
| 5 | 488.8 | 822.2 | +68.2% | 3.596 |
Which switchgear is at risk. Against a 1000 MVA busbar rating:
The bus that fails is not the bus the machine was connected to. Bus 5 rose the most in percentage terms and remains the weakest bus in the system; bus 2 rose by less and broke the rating, because it started closest to it. A fault-level assessment must be run at every bus, not at the point of connection.
Why the effect reaches so far. Compare with the earthing-transformer result of Set 22, where adding a zero-sequence earth point changed one bus by 73% and the others by 2 to 13%. Here every bus moves by at least 19.5%:
In the positive-sequence network every bus is coupled to every other, because there is no delta winding to sever anything. A change in the positive-sequence network is a system-wide event; a change in the zero-sequence network is usually a local one.
The planning consequence. Sixty megavolt-amperes of new generation — a machine whose own contribution is 333 MVA against the 833 MVA already present at bus 2 — raised that bus's fault level by 30%. Fault level does not grow in proportion to installed capacity; it grows in proportion to installed capacity divided by reactance, and a modern machine has a lower \(x''_d\) than the ones it joins. Every connection study must therefore include the fault-level check, and it is the reason a distribution utility can refuse a generator connection on switchgear grounds alone.
Three 25 MVA, 11 kV generators, each with \(x''_d = 0.14\) on its own rating, are to run in parallel on a busbar whose existing switchgear is rated 500 MVA breaking. Show that the arrangement is inadmissible, size an identical current-limiting reactor for each machine lead in per unit, in ohms and as a percentage of the machine rating, verify the full-load voltage drop it causes, and find the duty on a machine-lead breaker for a fault between a generator and its own reactor. Compare with the alternative of splitting the busbar.
Everything on a 100 MVA base at 11 kV:
The arrangement as it stands. Three identical shunt branches in parallel:
Over by 7.1%. Not a large exceedance, but a breaker is not a component one operates 7% beyond its rating — the failure mode is a restrike and a busbar fire, not a gradual degradation.
Sizing the reactor. With \(X_r\) in each lead the three branches remain in parallel, each of \(0.560+X_r\), so the required Thévenin impedance follows directly from the rating:
Write the new Thévenin impedance symbolically in terms of \(X_r\), set the resulting fault level equal to the switchgear rating, and solve. Everything else in the problem is a consequence of the 0.0400 obtained here.
In ohms and as a percentage:
One per cent. The percentage reactance of a reactor on the rating of the circuit it occupies is, to a good approximation, exactly the full-load voltage drop it imposes — so this reactor costs 1% of regulation, which is unobtrusive. A 10% reactor would not be.
The drop, computed directly to confirm the shortcut:
The fault between a machine and its own reactor. That machine's own contribution does not pass through its lead breaker; what the breaker interrupts is everything arriving from the busbar, which is the other two branches in parallel plus the faulted machine's own reactor in series:
Comfortably inside the 500 MVA rating. The reactor that was installed to protect the busbar also relieves the machine-lead breakers, which is a free benefit of the generator-reactor arrangement and one that a feeder-reactor arrangement does not provide.
The busbar duty and the making check. At the limiting 500 MVA:
And the reactors themselves must carry 26.24 kA for the full short-time duration without their air-cored windings deforming — a mechanical specification quite separate from their reactance.
The alternative: split the busbar. Operating the board as two sections, two machines on one and one on the other:
Far below 500 MVA, achieved with no hardware and no voltage drop at all. The price is redundancy: each section must carry its own load unaided, a fault on one section loses its machines outright, and the open tie must be closed for maintenance — at which moment the fault level returns to 536 MVA. Bus splitting is free in capital and expensive in operational flexibility; a reactor is the reverse.
Two 33 kV buses in a study on a 100 MVA base have \(Z_1 = Z_2 = j0.12\) per unit. Bus A is at the terminals of a solidly earthed transformer with \(Z_0 = j0.075\); bus B is earthed through a neutral reactor and has \(Z_0 = j0.20\). Find the three-phase and single line-to-ground fault currents at each, say which fault governs the breaker rating at each bus, and check both against the ratio rule.
The base current at 33 kV:
The three-phase fault is the same at both buses, because it involves the positive-sequence network alone:
The earth fault puts the three networks in series (Set 23), and the phase current is three times the sequence current:
The ratio rule confirms both without any of that arithmetic. With \(k = Z_0/Z_1\):
The rule crosses unity at \(k=1\): the earth fault is worse wherever \(Z_0 < Z_1\) and milder wherever it is not. That single comparison, made before any calculation, tells you which answer to expect.
Which governs:
A breaker at bus A rated on the three-phase fault would be 14% short. The mechanism is not exotic: a solidly earthed transformer is a stiffer zero-sequence source than the network is a positive-sequence one, so the earth path is the lower impedance — and that is precisely the situation at every transformer terminal, which is where busbars are.
The theoretical bound. As \(Z_0\to0\) the ratio approaches \(3/2 = 1.5\), so an earth fault can never exceed a three-phase fault by more than 50%. Bus A's 14.3% is unremarkable; ratios of 20 to 30% are common at large solidly earthed generator-transformers, and reaching 1.4 requires a zero-sequence impedance close to zero.
What the neutral reactor bought and what it cost. At bus B the earth fault is 18% below the three-phase value, so the switchgear is sized by the balanced fault and the earth-fault duty on the transformer neutral is modest. The cost is that the healthy-phase voltage rise is larger and the earth-fault current may fall so low that sensitive earth-fault protection is needed to detect it at all — the design trade that Set 22's effective-earthing criterion \(X_0/X_1 \le 3\) is written to bound.
One caution about motors. The positive- and negative-sequence figures include every rotating machine on the bus; the zero-sequence figure usually does not, because a motor is fed through a delta winding or has an unearthed star. So motor contribution inflates \(I_{3\phi}\) and leaves \(I_{LG}\) nearly untouched, and a bus with heavy motor load is more likely to be governed by the three-phase fault than these impedances alone suggest.
A new 33 kV indoor switchboard is to be specified. The grid fault level at the 132 kV supply point is 6000 MVA. Two 63 MVA, 132/33 kV transformers of 12.5% reactance run in parallel, and 40 MVA of induction motors rated above 1000 hp, with \(X''_d = 0.17\), are connected to the 33 kV board. Protection clears a busbar fault in 0.5 s. Working on a 100 MVA base:
- Find the fault level and the symmetrical, momentary and interrupting currents.
- Select from the 36 kV list — 25 or 31.5 kA breaking, 62.5 or 78.8 kA peak making, 3 s short-time.
- The utility intends to add a third identical transformer within five years. Re-run the selection and state what should be bought now.
Part 1 — the impedances. The grid becomes a reactance from its declared fault level; the transformers convert from their own rating:
The motors, in both networks. Above 1000 hp, so \(1.0X''_d\) in the first cycle and \(1.5X''_d\) at interruption:
The three duties:
\(\mathrm{MF}=1.0\) is justified: everything except the motors arrives through two transformers from a remote grid, so the composite \(X/R\) at the board is well under 17.
Part 2 — the selection as things stand. Against the 25 kA unit:
| Rating | 36 kV, 25 kA | Duty | Margin |
|---|---|---|---|
| Breaking | 25 kA | 17.84 kA | +40.1% ✓ |
| Making | 62.5 kA peak | 51.88 kA | +20.5% ✓ |
| Short-time | 25 kA, 3 s = 1875 kA²s | 17.84 kA, 0.5 s = 159 kA²s | ample ✓ |
Every row passes, the smallest margin being 20.5% on the making current. On today's system the 25 kA breaker is the correct and economical choice.
Part 3 — with the third transformer. Three in parallel:
The 25 kA breaker now fails:
And 4.7% of breaking margin is not a margin at all: raising the prefault voltage from 1.00 to 1.05 pu, which is a legitimate operating condition, takes the interrupting duty to 25.07 kA and the breaker is over its rating on that row too.
The 31.5 kA unit against the future case:
All rows pass with the smallest margin at 15.6%, which is the accepted lower bound of normal practice.
The recommendation, and its arithmetic. Buy 36 kV, 31.5 kA now. The premium over a 25 kA board is a few per cent of the switchgear cost; replacing an entire indoor board five years after commissioning costs the equipment again plus an outage of the whole substation. The making current is the row that decides it, and it is the row that would have been passed over by anyone checking breaking capacity alone.
A closing check on the motors. Delete them and the future first-cycle current falls from 25.25 to 21.13 kA and the crest from 68.16 to 57.05 kA — inside the 25 kA breaker's ratings. The entire decision turns on 40 MVA of motor load that no supply-side calculation would ever see.
Practice Problems
Work each on paper before opening the answer. The answer is given so you can check yourself; the method is deliberately not.
P1. A bus has \(Z_{kk}=j0.08\) pu on a 100 MVA base at 220 kV. Find the three-phase fault current in kA and the fault level.
Show answer
\(I_f = 12.5\) pu; \(I_{base}=0.26243\) kA, so \(\mathbf{3.280}\) kA and \(\mathbf{1250}\) MVA. Problem 1.P2. A utility declares 2500 MVA at its supply point. What reactance represents it on a 100 MVA base?
Show answer
\(X = 100/2500 = \mathbf{0.0400}\) pu. A declared fault level carries its own base. Problem 1.P3. For the five-bus network of Problem 3, find the fault current and fault level at bus 3.
Show answer
\(1/0.17377 = \mathbf{5.755}\) pu \(=\mathbf{2.517}\) kA; \(S_{sc}=\mathbf{575.5}\) MVA.P4. For a bolted fault at bus 1 of the same network, what voltage remains at bus 5?
Show answer
\(1 - 0.10160/0.12514 = \mathbf{0.188}\) pu — a sag of 81.2%. Bus 5 is far from bus 1 in impedance but has nothing holding it up. Problem 4.P5. A breaker is rated 40 kA symmetrical breaking. What is its rated making current at 50 Hz and at 60 Hz?
Show answer
\(2.5\times40=\mathbf{100}\) kA peak and \(2.6\times40=\mathbf{104}\) kA peak. Problem 13.P6. Find the breaking capacity in MVA of a 145 kV, 31.5 kA breaker.
Show answer
\(\sqrt3\times145\times31.5 = \mathbf{7911}\) MVA. Use the rated voltage 145 kV, not the nominal 132 kV.P7. Find the rms and crest asymmetry factors half a cycle after inception for \(X/R = 25\).
Show answer
\(k_{rms}=\sqrt{1+2e^{-2\pi/25}}=\mathbf{1.599}\); \(k_{crest}=\sqrt2(1+e^{-\pi/25})=\mathbf{2.661}\). Problem 9.P8. A 5 MVA group of induction motors above 1000 hp has \(X''_d=0.17\). What reactance does it present in each network on a 100 MVA base?
Show answer
\(0.17\times20 = 3.40\) pu, so \(\mathbf{3.40}\) in the first-cycle network and \(1.5\times3.40=\mathbf{5.10}\) in the interrupting network. Problem 10.P9. What is done with induction motors below 50 hp?
Show answer
\(\mathbf{1.67X''_d}\) in the first-cycle network, or neglected; neglected entirely in the interrupting network. Their contribution is gone within a cycle. Problem 10.P10. A 33 kV board has a fault level of 863 MVA. What is the symmetrical fault current?
Show answer
\(863/(\sqrt3\times33) = \mathbf{15.10}\) kA. Problem 20.P11. A generator of \(j0.30\) pu is added at bus 5 of the five-bus network, where \(Z_{55}=j0.20457\). Find the new \(Z_{55}\).
Show answer
\(0.20457\parallel0.300 = 0.20457\times0.300/0.50457 = \mathbf{j0.12163}\) — a 41% reduction, so a 68% rise in fault level. Problem 17.P12. A reactor of 0.0400 pu on a 100 MVA base sits in an 11 kV circuit. Give its ohmic value, and its percentage on a 25 MVA machine rating.
Show answer
\(Z_{base}=1.21\ \Omega\), so \(\mathbf{0.0484\ \Omega}\); on 25 MVA, \(0.04\times0.25 = \mathbf{1.00\%}\) — which is also its full-load voltage drop. Problem 18.
Challenge Problems
Three problems that need an idea rather than a formula — the places where a correct calculation still gives the wrong equipment.
C1 — The study that came out low. A fault study of an 11 kV plant board predicts 18.0 kA symmetrical. A real fault two years later is recorded at 21.6 kA. Rank the possible causes by probability, quantify each, and say which single measurement would settle the matter.
Show answer
What has to be explained. A ratio of \(21.6/18.0 = 1.200\), which requires the Thévenin impedance to be 16.7% smaller than the study assumed:
\[ \frac{X_{true}}{X_{study}} = \frac{1}{1.200} = 0.833 \]Cause 1: the recording is not a symmetrical current. The commonest and the cheapest to check. A disturbance recorder reports the rms of what it measured, and a fault caught near full offset gives \(1.6\times18.0 = 28.8\) kA in the first cycle, falling towards 18 kA as the offset decays. A reading of 21.6 kA is exactly what a recorder would report from a partially offset wave read a cycle or two in. Settle it by looking at the recorded waveform rather than the reported number, and comparing the first-cycle peak with the steady peak.
Cause 2: motors omitted or under-counted. Problem 12 showed that motors add 22.7% to the first-cycle current at a plant of this kind, which alone accounts for the whole discrepancy. Two years is more than enough for a plant to add several megawatts of drives without anybody re-running the study. Settle it by comparing the motor schedule against the installed list.
Cause 3: the utility has strengthened its network. A supply-point fault level of 300 MVA rising to 400 MVA moves \(1/X_{util}\) from 3.000 to 4.000, which raises a 4.639 pu total to 5.639 pu — 21.6%. Settle it by asking for the current declared fault level, which the utility revises when it reinforces.
Cause 4: transformer impedance tolerance. IEC permits \(\pm7.5\%\) on a two-winding transformer's declared impedance; at the low end this gives 8.1% more current. Real but too small alone.
Cause 5: prefault voltage. The study used 1.00 pu; the board may have been at 1.05. Worth 5%, and again too small alone.
The ranking, and why. Causes 1 and 2 each explain the whole gap; causes 3, 4 and 5 explain a fifth to a quarter of it each and are the kind of thing that compounds. The one measurement that settles it is the recorded waveform — if it shows offset, the answer is cause 1 and the study was right; if the wave is symmetrical from the first cycle, the study's network is wrong and causes 2 and 3 are the candidates.
The general lesson. When a study disagrees with a measurement, first establish that the two quantities are the same quantity. Symmetrical rms, asymmetrical rms and crest differ by factors of 1.6 and 2.7, and a large fraction of apparent discrepancies are unit errors dressed up as engineering ones.
C2 — The breaker that met its rating and failed. A 145 kV breaker rated 31.5 kA clears terminal faults reliably but fails on a fault a few kilometres out on one of its lines, where the current is only 28 kA. Explain, and quantify the duty the breaker actually met. Take the line surge impedance as 450 Ω.
Show answer
The current is not the whole duty. Interruption succeeds if the gap's dielectric strength recovers faster than the transient recovery voltage rises across it. A breaker's rating fixes the current it can interrupt and the TRV envelope it can withstand while doing so, and the second is the one a short-line fault attacks.
Why a short line is worse than a terminal fault. After the arc extinguishes, the line-side terminal is left connected to a length of line with a travelling wave on it. The voltage there collapses and rebuilds as a sawtooth, at a rate set by the current slope at zero and the line's surge impedance:
\[ \left.\frac{di}{dt}\right|_{i=0} = \sqrt2\,\omega I, \qquad \frac{dv}{dt} = Z_0\,\frac{di}{dt} \]The numbers. With \(I = 28\) kA at 50 Hz:
\[ \frac{di}{dt} = \sqrt2\times2\pi\times50\times28\,000 = 12.44\times10^{6}\ \text{A/s} = 12.44\ \text{A/}\mu\text{s} \]\[ \frac{dv}{dt} = 450\times12.44 = 5.60\ \text{kV/}\mu\text{s} \]Against the rating. The standard terminal-fault TRV requirement for a 145 kV breaker at full breaking current is 2 kV/µs. The short-line fault presents 5.6 kV/µs — 2.8 times the rate the breaker was tested to — while drawing 11% less current than the terminal fault it clears without difficulty.
Why "a few kilometres" and not at the terminals. At the terminals there is no line-side stub, so no sawtooth: the TRV is the slow, source-side one. Very far out, the current has fallen enough that \(di/dt\) and hence \(dv/dt\) are small. The worst case is a fault at 75 to 90% of the terminal fault current — a kilometre or two on a 145 kV line — which is exactly why IEC defines separate short-line-fault test duties L90 and L75.
The remedy, in order of cost: specify the short-line-fault duty explicitly at purchase; fit opening resistors or grading capacitors, which lower \(dv/dt\) by adding capacitance across the interrupter; or add a few nanofarads of line-side capacitance at the terminal, which blunts the first sawtooth. Doing nothing and hoping the current margin covers it is the mistake that produced the failure.
The lesson. A fault study produces a current, and a current is necessary but not sufficient. The rate of rise of recovery voltage, the operating sequence under autoreclose and the out-of-phase switching duty are all independent tests a breaker must pass, and none of them is implied by a comfortable margin on \(I_{sc}\).
C3 — When does the board run out? The 33 kV board of Problem 20 was built with 36 kV, 25 kA switchgear: duties 19.22 kA first cycle, 51.88 kA crest, 17.84 kA interrupting, against ratings of 25 kA and 62.5 kA peak. Fault level in the area grows at 4% a year. Find the year in which each rating is breached, say which one goes first and why, and set out the options at that point with their costs.
Show answer
Both duties grow at the same rate, since both are proportional to the current, so the question is which has the smaller headroom in ratio terms:
\[ \text{making: } \frac{62.5}{51.88} = 1.2047, \qquad \text{breaking: } \frac{25}{17.84} = 1.4013 \]\[ n = \frac{\ln(\text{headroom})}{\ln 1.04} \]\[ n_{making} = \frac{0.18626}{0.039221} = \mathbf{4.75\ \text{years}}, \qquad n_{breaking} = \frac{0.33744}{0.039221} = 8.60\ \text{years} \]The making current goes first, by nearly four years, and it goes first for a structural reason rather than an accidental one: the momentary duty is computed from \(X_{first}\) and the interrupting duty from the larger \(X_{int}\), so the first-cycle current is always the bigger of the two, while the two nameplate figures are locked together by the fixed ratio \(i_p = 2.5I_{sc}\). Any board with significant motor load exhausts its close-and-latch rating before its breaking rating.
What that means operationally. A board past its making rating but inside its breaking rating is not immediately dangerous in normal service — it will still clear a fault that develops while it is closed. It fails when it is closed onto a standing fault: an autoreclose onto a persistent fault, a maintenance earth left on, or a closing onto a cable damaged during work. The failure mode is contact welding and a failure to open at all, which is worse than a failure to interrupt.
The options at year five, cheapest first:
\[ \begin{array}{lll} \text{Split the bus (open the section tie)} & \text{immediate, no capital} & \text{halves redundancy} \\ \text{Block autoreclose on the board} & \text{a setting change} & \text{removes the duty, not the risk} \\ \text{Bus-section reactor} & \text{moderate} & \text{carries only interchange current} \\ \text{Higher-impedance transformers} & \text{at next replacement} & \text{worse regulation for life} \\ \text{Replace the switchboard} & \text{highest} & \text{an outage of the whole substation} \end{array} \]The decision that should have been taken at year zero. Problem 20 recommended 31.5 kA. Its headroom would be \(78.8/51.88 = 1.519\), giving \(\ln(1.519)/\ln(1.04) = 10.7\) years on the making current and 14.5 years on breaking. A single step up the standard list bought six extra years for a few per cent of the board's price — which is the whole argument for specifying switchgear against the system's future rather than its present.
The caution on the growth rate. Four per cent a year is a planning figure, not a law. Fault level moves in steps, not exponentially: a new transformer, a new generator or a reconfigured supply moves it by 20 or 30% overnight, and nothing at all happens in between. The exponential is a way of budgeting for steps whose timing is unknown, and the right response to it is a periodic re-run of the study, not a calculation done once at commissioning.
Multiple-Choice Questions
MCQ 1. A bus has \(Z_{kk}=j0.10\) pu on a 100 MVA base. Its fault level is:
(a) 10 MVA (b) 100 MVA (c) 1000 MVA (d) 0.1 MVAShow answer
(c). \(S_{sc}=\mathrm{MVA}_{base}/|Z_{kk}| = 100/0.10\). Answer (a) is the base times the impedance rather than divided by it. Problem 1.MCQ 2. For a fault at bus \(k\), column \(k\) of \(\mathbf{Z}_{\text{bus}}\) supplies:
(a) the fault current (b) the voltage at every bus (c) the line reactances (d) nothing beyond the diagonalShow answer
(b), through \(V_i = V_f(1-Z_{ik}/Z_{kk})\). The diagonal alone gives the current, which is why (a) names only one entry of the column. Problem 4.MCQ 3. The rated short-circuit making current of a 50 Hz breaker is:
(a) \(1.6I_{sc}\) (b) \(2.5I_{sc}\) (c) \(2.7I_{sc}\) (d) \(\sqrt2 I_{sc}\)Show answer
(b). Each distractor is a real number from elsewhere: 1.6 is the momentary rms multiplier, 2.7 the ANSI crest multiplier applied to \(E/X_{first}\), and \(\sqrt2\) the crest of a wave with no offset at all. Problem 13.MCQ 4. In the interrupting network, an induction motor of 100 hp is represented by:
(a) \(1.0X''_d\) (b) \(1.2X''_d\) (c) \(1.5X''_d\) (d) \(3.0X''_d\)Show answer
(d). It is above 50 hp but not above 250 hp at 3600 rpm, so it falls in the "all other induction motors" row: \(1.2X''_d\) in the first cycle and \(3.0X''_d\) at interruption. Choosing (b) is answering for the wrong network. Problem 10.MCQ 5. Between the first-cycle and interrupting networks, a turbine generator's reactance is multiplied by:
(a) 1.0 (b) 1.5 (c) 3.0 (d) it is neglectedShow answer
(a). Its field winding still carries current, so its flux has barely decayed in three cycles. Only machines that lost their excitation when the bus collapsed are de-rated. Problem 10.MCQ 6. A slower breaker, all else equal, has an interrupting duty that is:
(a) larger (b) smaller (c) unchanged (d) larger only if motors are presentShow answer
(b). Its contacts part later, by which time more of the DC offset and more of the subtransient contribution have decayed. Speed is bought for stability and paid for at the interrupter. Problem 11.MCQ 7. The largest possible ratio of crest current to symmetrical rms current is:
(a) 1.414 (b) 2.0 (c) 2.5 (d) 2.828Show answer
(d) \(=2\sqrt2\), the lossless limit where nothing decays: full offset added to a crest. The IEC 2.5 sits below it because a real circuit has resistance. Problem 9.MCQ 8. At a bus, a single line-to-ground fault exceeds a three-phase fault when:
(a) \(Z_0 > Z_1\) (b) \(Z_0 < Z_1\) (c) \(Z_0 = Z_1\) (d) neverShow answer
(b). The ratio is \(3/(2+k)\) with \(k=Z_0/Z_1\), which exceeds 1 exactly when \(k<1\). Its maximum is 1.5. Problem 19.MCQ 9. Treating plant motors as passive load in an industrial fault study:
(a) overstates every duty (b) understates every duty (c) affects the interrupting duty more than the momentary (d) has no effect on ratingsShow answer
(b), and by more in the first cycle than at interruption — so (c) has the comparison backwards. In Problem 12 the understatement was 22.7% momentary against 13.7% interrupting.MCQ 10. A current-limiting reactor is built without an iron core because:
(a) it is cheaper (b) it must not saturate under fault current (c) iron would raise the losses (d) it must be lighterShow answer
(b). A saturating core would lose exactly the reactance the reactor was installed to provide, at exactly the current at which it is needed. Problem 18.MCQ 11. A 25 kA, 3 s short-time rating may be read as:
(a) 43.3 kA for 1 s (b) 14.4 kA for 9 s (c) both (d) neitherShow answer
(b) only. The \(I^2t\) trade is valid towards longer times and lower currents. Upward it is barred by the peak withstand: 43.3 kA implies a 108 kA crest against a 62.5 kA rating. Problem 16.MCQ 12. Adding a generator at one bus of a meshed positive-sequence network:
(a) raises the fault level at that bus only (b) raises it at every bus (c) lowers it elsewhere (d) has no effect beyond two busesShow answer
(b). Every bus is coupled to every other in the positive-sequence network, so the rank-one correction \(Z_{ik}Z_{kj}/(Z_{kk}+z_b)\) is nonzero everywhere. In Problem 17 the smallest rise was 19.5%. Contrast the zero-sequence network, where a delta winding makes the effect local.
Key Formulas
| Statement | Relation | Notes |
|---|---|---|
| Three-phase fault current | \(I_f = V_f/(Z_{kk}+Z_f)\) | Diagonal entry only |
| Fault level | \(S_{sc} = \mathrm{MVA}_{base}/|Z_{kk}|_{pu}\) | Exact when \(V_f=1.0\) |
| Utility source | \(X_{source} = \mathrm{MVA}_{base}/S_{sc}\) | A declared level is a full model |
| Post-fault voltages | \(V_i = V_f\left(1 - Z_{ik}/Z_{kk}\right)\) | One column, every bus |
| Branch current | \(I_{ij} = (V_i-V_j)/z_{ij}\) | Sum into the faulted bus \(=I_f\) |
| Source contribution | \(I_{G} = (V_f-V_{bus})/x_G\) | Or the branch currents out of its bus |
| Fault through \(Z_f\) | \(I_f/I_f^{bolted} = 1/(1+Z_f/Z_{kk})\) | \(V_k = Z_fI_f \ne 0\) |
| Fault on a line at \(\alpha\) | remove, Type 2 at \(\alpha z\), Type 4 at \((1-\alpha)z\) | Minimum current is inside the line |
| Adding a shunt at bus \(k\) | \(Z_{ij}^{new} = Z_{ij} - Z_{ik}Z_{kj}/(Z_{kk}+z_b)\) | Type 3; check \(Z_{kk}^{new}=Z_{kk}\parallel z_b\) |
| Asymmetry, rms | \(k_{rms}=\sqrt{1+2e^{-2\pi R/X}}\) | 1.6 at \(X/R=30\); limit \(\sqrt3\) |
| Asymmetry, crest | \(k_{crest}=\sqrt2\left(1+e^{-\pi R/X}\right)\) | 2.7 at \(X/R=30\); limit \(2\sqrt2\) |
| The two duties | \(I_{mom}=1.6E/X_{first}\), \(I_{int}=\mathrm{MF}\cdot E/X_{int}\) | \(i_{mom,crest}=2.7E/X_{first}\) |
| Machine de-rating | \(1.0/1.5/3.0 \times X''_d\) | Generator / large motor / small motor |
| Making current | \(i_p = 2.5I_{sc}\) (50 Hz), \(2.6I_{sc}\) (60 Hz) | From \(T=45\) ms in both cases |
| Breaking capacity | \(S = \sqrt3\,U_r I_{sc}\) | Rated voltage, not nominal |
| ANSI capability | \(I_{cap}=\min(I_rV_{max}/V,\ KI_r)\) | Flat below \(V_{max}/K\) |
| Short-time withstand | \(I_k^2t_k = I^2t\), downward only | Upward barred by the peak rating |
| Thermal equivalent | \(I_{th}=I\sqrt{1+m}\), \(m=T(1-e^{-2t/T})/t\) | \(T = (X/R)/\omega\) |
| Reactor sizing | \(X_{th}^{new} \ge \mathrm{MVA}_{base}/S_{sc}^{allowed}\) | Percentage on circuit rating = full-load drop |
| Which fault governs | \(I_{LG}/I_{3\phi} = 3/(2+Z_0/Z_1)\) | Earth fault worse when \(Z_0<Z_1\); max 1.5 |
Common Mistakes
Checking the breaking rating and stopping there. The momentary duty is computed from a smaller reactance than the interrupting duty, while the two nameplate figures are locked together by \(i_p=2.5I_{sc}\) — so a breaker can pass on breaking and fail on making. It did exactly that in Problem 14, by 4.9%.
Treating motors as passive load. The single commonest reason an industrial study comes out low. In Problem 12 the motors were worth 22.7% of the first-cycle current, and Problem 14 showed that this is the difference between a 25 kA board and a 31.5 kA one.
Using the same machine reactances in both networks. A generator is unchanged; a synchronous or large induction motor is multiplied by 1.5 and a small induction motor by 3.0, at interruption. Using first-cycle values throughout overstates the interrupting duty; using interrupting values throughout understates the momentary one, which is the dangerous direction — Problem 10.
Rating a line breaker for the full bus fault level. No breaker interrupts the total: it interrupts its own branch. In Problem 5 the largest branch current was 72% of the fault current, and the busbar figure over-specifies every line breaker on it.
Assuming the smallest fault current on a line is at its far end. True only for a radial feed. With both ends fed the minimum lies inside the line — at 74.6% in Problem 8 — and grading an overcurrent relay on the end-of-line figure leaves it short.
Reading a short-time rating upward. 25 kA for 3 s does not mean 43.3 kA for 1 s, because the implied 108 kA crest exceeds the 62.5 kA peak withstand. The \(I^2t\) trade works towards longer times only — Problem 16.
Comparing a symmetrical study with an asymmetrical measurement. Symmetrical rms, asymmetrical rms and crest differ by 1.6 and 2.7, so a fifth of apparent discrepancies between a study and a disturbance record are unit errors — Challenge C1.
Using nominal voltage instead of rated voltage in a breaking capacity. \(\sqrt3\times11\times25\) is not the capacity of a 12 kV, 25 kA breaker; it understates it by 8.3% — Problem 13.
Applying the inverse-voltage rise without the ANSI \(K\) ceiling. At 11 kV a 15 kV, 18 kA, \(K=1.3\) breaker is worth 23.40 kA, not 24.55 kA, and the difference decides whether it serves — Problem 15.
Checking the thermal rating against the main clearing time. The duration that matters is the backup clearance, because that is what the equipment must survive while another breaker fails — Problem 16.
Assuming a new machine only affects its own bus. In the positive-sequence network every bus is coupled to every other; in Problem 17 the bus that breached its rating was three lines away from the new generator.
Forgetting that the earth fault can be the larger one. Wherever \(Z_0<Z_1\) — at every solidly earthed transformer terminal — the single line-to-ground fault governs the rating, by up to 50%. Problem 19.
Part 5 is complete. Every fault type has been formulated, every network built, and the currents they produce have been carried through to a rating on a nameplate. What has not been asked anywhere in these five parts is what the system does while all this is happening — the machines have been treated as constant voltages behind constant reactances, and their rotors have been assumed to stay where they were.
They do not. A fault removes the electrical torque from every machine that feeds it while the mechanical torque continues unchanged, and the rotors accelerate for as long as the fault lasts. Part 6 replaces the constant-voltage source by the swing equation, and the clearing time that appeared here only as a thermal duration becomes the quantity on which the whole system's survival depends. The breaker chosen in Problem 20 for its interrupting capability will be chosen again in Part 6 for its speed, and the two specifications are not the same.