Part 5 · Chapter 21

Symmetrical Faults and Short-Circuit Transients

A three-phase fault leaves the network balanced, so one phase still tells the whole story — but the current it draws is neither constant nor sinusoidal, and calculating it means understanding both the decaying DC offset of the circuit and the decaying reactance of the machine.

Electric Power Systems Prof. Mithun Mondal Reading time ≈ 50 min
i What you'll learn
  • How faults are classified into shunt and series types, why only the three-phase fault is symmetrical, and why the rarest fault is the one equipment is rated for.
  • Why closing an inductive circuit onto a sinusoid produces a decaying DC offset, and how the instant of closure decides whether the first peak is one times or nearly twice the symmetrical peak.
  • Why a synchronous machine presents three different direct-axis reactances \(X_d'' < X_d' < X_d\), derived from the constant flux linkage theorem.
  • How to read \(X_d''\), \(X_d'\) and \(X_d\) off a short-circuit oscillogram, and which one each calculation needs.
  • How a symmetrical fault is solved by Thevenin's theorem and superposition, with the prefault load current restored afterwards.
  • How one column of the \(\mathbf{Z}_{bus}\) of Chapter 17 gives every bus voltage and every line current during the fault.
  • How short-circuit MVA, momentary duty and interrupting duty follow from the same calculation, and how a breaker is chosen from them.
Section 21-1

What a Fault Is, and Which Ones Matter

Everything in Parts 3 and 4 of this book assumed a network in its intended configuration: conductors insulated from each other and from earth, three phases balanced, currents set by load rather than by geometry. A fault is any failure of that assumption — any event that interferes with the normal flow of current. Insulation ages and punctures, a lightning stroke flashes an insulator string over, a crane arm or a falling branch bridges two conductors, ice or wind brings a span to the ground, a switching operation is carried out on the wrong circuit. On transmission lines at 115 kV and above the dominant cause by a wide margin is lightning, which ionises the air across an insulator string and leaves a low-impedance path to the earthed tower.

Two families are distinguished by what the failure does to the circuit. A shunt fault, or short circuit, creates an unintended connection — conductor to earth, or conductor to conductor. A series fault is an unintended break: one or two broken conductors, or a breaker whose three poles do not open together. The two behave in opposite ways. A shunt fault raises current and depresses voltage; a series fault reduces current in the affected phases and raises the voltage across the break. Shunt faults are far more common and far more damaging, and they are what Part 5 is about.

Shunt faultPhases involvedSymmetryShare of all faults
Single line-to-ground (LG)one phase and earthunsymmetrical≈ 70 %
Line-to-line (LL)two phasesunsymmetrical≈ 15 %
Double line-to-ground (LLG)two phases and earthunsymmetrical≈ 10 %
Three-phase (LLL or LLLG)all threesymmetrical≈ 5 %

Only the last row leaves the system balanced. If all three phases are shorted together at the same point — with or without a connection to earth — the network retains the three-fold symmetry that Chapter 3 exploited, the three phase currents remain equal in magnitude and \(120^\circ\) apart, and the entire calculation can still be carried out on a single phase using the per-phase equivalent circuit and the per-unit impedance diagram of Chapter 4. That is why this chapter comes first: the symmetrical fault is the only one that needs no new machinery beyond what Part 4 already built.

The other three rows destroy the symmetry, and per-phase analysis collapses with it. Chapter 22 introduces the transformation that restores it, Chapter 23 builds the three networks that transformation calls for, and Chapter 24 connects them for each fault type. So the rare fault is treated first and the common ones second, which looks backwards until one notices the second reason for the ordering.

The rarest fault sets the rating. A bolted three-phase fault is normally the most severe short circuit a given point of the network can experience, because it collapses all three phase voltages simultaneously and every source in the system feeds it through the positive-sequence impedance alone. Equipment is therefore specified against the three-phase fault level even though nineteen faults in twenty are something else. The exception worth remembering is a solidly earthed bus close to a generator, where the single line-to-ground current can exceed the three-phase value — Chapter 24 shows why.

Two currents matter, and they are not the same current. The first is the current flowing in the first cycle or two after inception, which the closed breaker contacts and the busbars must survive mechanically and thermally. The second is the current still flowing three to eight cycles later, when the protective relay has decided (Chapter 36) and the breaker contacts actually part — that is the current the arc must interrupt. Between the two instants the current falls, for two independent reasons that occupy the next four sections: the circuit sheds a DC transient, and the machine raises its own reactance.

Section 21-2

Switching an RL Circuit: Where the DC Offset Comes From

Strip the problem to its smallest honest form. An unloaded transmission line, with its shunt capacitance neglected, is a series \(R\)–\(L\) branch fed from a stiff sinusoidal source. A fault at the far end is the closing of a switch across that branch at some instant \(t=0\). Before closure the current is zero; after closure it is governed by

The switched RL circuit
\[ L\frac{di}{dt} + Ri = \sqrt{2}\,V\sin(\omega t + \alpha), \qquad i(0^-)=0 \]

Here \(V\) is the rms source voltage and \(\alpha\) is the phase angle of that voltage at the instant of closure — a number the fault chooses, not the engineer. The general solution is the sum of a particular integral (the steady-state sinusoid) and a complementary function (the natural response of an \(RL\) loop, a decaying exponential):

General solution
\[ i(t) = \underbrace{\frac{\sqrt2\,V}{Z}\sin(\omega t + \alpha - \theta)}_{\text{steady state, } i_{ac}} \;+\; \underbrace{A\,e^{-t/\tau}}_{\text{natural response}}, \qquad Z=\sqrt{R^2+(\omega L)^2},\;\; \theta=\tan^{-1}\!\frac{\omega L}{R},\;\; \tau=\frac{L}{R} \]

The constant \(A\) is not free. Current in an inductance cannot change instantaneously, so \(i(0^+) = i(0^-) = 0\). Setting \(t=0\) in the general solution and solving for \(A\) gives \(A = -(\sqrt2 V/Z)\sin(\alpha-\theta)\), and with that one substitution the whole behaviour of the short-circuit current is fixed.

🔑
Short-circuit current of an RL circuit
\[ i(t) = \frac{\sqrt2\,V}{Z}\Big[\underbrace{\sin(\omega t + \alpha - \theta)}_{\text{symmetrical AC}} \;-\; \underbrace{\sin(\alpha-\theta)\,e^{-t/\tau}}_{\text{DC offset}}\Big] \]

The AC term is the current that would flow if the circuit had been shorted forever. The DC term exists solely to force the total to zero at \(t=0\); it carries no energy from the source and decays with the circuit time constant \(\tau = L/R = X/(\omega R)\).

The DC offset is therefore not a separate physical current but the price of continuity. The steady-state sinusoid at \(t=0\) has the value \((\sqrt2 V/Z)\sin(\alpha-\theta)\), which is generally not zero; the exponential starts at exactly minus that value and cancels it, then decays away and leaves the sinusoid behind. Its initial magnitude is set entirely by \(\alpha-\theta\), the angular distance between the instant of closure and the natural zero crossing of the steady-state current.

Two special cases bracket everything. If \(\alpha = \theta\), the closure happens exactly when the steady-state current passes through zero: no offset is needed, and the current is a pure sinusoid from the first instant. If \(\alpha - \theta = \pm 90^\circ\), the closure happens when the steady-state current would be at its peak: the offset is a full \(\sqrt2 V/Z\), and the current is as asymmetric as it can be. In a power network \(X \gg R\), so \(\theta \approx 90^\circ\), and the worst case corresponds to \(\alpha \approx 0\) — a fault struck at the instant the driving voltage passes through zero.

A DC source shows none of this. Replace the sinusoid by \(V_{dc}\) and the same equation gives \(i = (V_{dc}/R)(1-e^{-t/\tau})\) — a single rising exponential whose shape does not depend on when the switch was closed, because a DC source has no phase. The dependence on the closing instant is entirely a consequence of the source being alternating, and it is what makes short-circuit current a statistical quantity rather than a deterministic one.
Section 21-3

The Worst Instant and the Asymmetry Factor

Take the worst case, \(\alpha-\theta=-90^\circ\), and write \(I=V/Z\) for the rms symmetrical current. The expression collapses to

Fully offset short-circuit current
\[ i(t) = \sqrt2\,I\Big[e^{-t/\tau} - \cos\omega t\Big] \]

The current never changes sign — it is a sinusoid riding on a positive exponential platform — and it reaches its largest value when \(\cos\omega t = -1\), that is half a cycle after inception, at \(t = T/2 = \pi/\omega\). Evaluating the exponential there and noting that \(t/\tau = \pi\omega R/(\omega X) = \pi R/X\) gives the peak directly.

🔑
Peak and rms of the offset current
\[ i_{peak} = \sqrt2\,I\left(1+e^{-\pi R/X}\right), \qquad I_{rms}(t) = I\sqrt{1+2e^{-2t/\tau}} \;\;\xrightarrow[\;t=T/2\;]{}\;\; I\sqrt{1+2e^{-2\pi R/X}} \]

The rms expression comes from adding an AC component of rms value \(I\) to a DC component of instantaneous value \(i_{dc}\) in quadrature of energy: \(I_{rms}=\sqrt{I^2+i_{dc}^2}\), with \(i_{dc}=\sqrt2 I e^{-t/\tau}\). Both multipliers depend on the single number \(X/R\).

The limiting values are instructive. If the circuit had no resistance at all the exponential would never decay, the peak would be \(2\sqrt2 I\) — the familiar doubling effect — and the rms would be \(\sqrt3\,I = 1.732\,I\). Real circuits fall short of this, and by how much is governed by \(X/R\) alone:

\(X/R\)Typical locationPeak multiplier \(1+e^{-\pi R/X}\)RMS multiplier \(\sqrt{1+2e^{-2\pi R/X}}\)
5distribution feeder, cable1.531.25
10medium transmission line1.731.44
15EHV line, large transformer1.811.52
30generator terminals1.901.62
\(\infty\)lossless limit2.001.73

The bold entry is the origin of a rule that every switchgear catalogue uses. Close to a generator, where \(X/R\) is of the order of \(30\), the rms current including the DC offset at the end of the first half cycle is about \(1.6\) times the symmetrical value. The factor \(1.6\) is not an arbitrary safety margin; it is \(\sqrt{1+2e^{-2\pi/30}}\), and Section 21-9 uses it exactly as it stands.

t i(t) T2T3T +√2I −√2I first peak = 1.73 × √2I DC offset √2I·e^(−t/τ) symmetrical case (α = θ) total, α − θ = −90°
The DC offset and the doubling effect, X/R = 10

One warning about three-phase systems. The three source voltages differ in phase by \(120^\circ\), so the three phases are closed at three different values of \(\alpha\). At most one phase can be fully offset; the other two carry smaller offsets, and the three offsets always sum to zero. A "symmetrical" three-phase fault is therefore symmetrical only in its AC component. The DC offsets are unequal, which is why the phase currents differ during the first few cycles even when the fault is perfectly balanced, and why breaker duty is quoted for the worst phase.

Section 21-4

Why a Synchronous Machine Has Three Reactances

The RL model of the last two sections assumed a source of fixed emf behind a fixed impedance. Applied to a real generator it is wrong, and wrong in a way that matters. Oscillograms of a machine short-circuited at its terminals show the AC component itself decaying — the envelope falls steeply for the first few cycles, then more gently, then settles. Since the terminal voltage was constant beforehand, the only way the current can fall is for the effective internal reactance to rise with time.

The mechanism is the constant flux linkage theorem: the flux linkage of any closed circuit of zero resistance cannot change instantaneously, and in a circuit of small resistance it changes only slowly, with that circuit's own time constant. A synchronous machine has three magnetically coupled circuits on the direct axis — the armature winding, the field winding, and the damper (amortisseur) bars — and the last two are closed loops of low resistance.

At the instant of short circuit the armature current jumps and its mmf tries to demagnetise the air gap. The damper circuit and the field circuit each respond by developing an induced current that holds their own flux linkage at its prefault value, which forces the armature flux to divert into leakage paths instead. Seen from the armature terminals, the magnetising reactance \(x_{ad}\) is therefore shunted by the leakage reactances of whichever rotor circuits are still holding their flux. Three stages follow, in the order in which the rotor circuits give up.

The three direct-axis reactances as ladder networks
\[ X_d'' = x_l + \big(x_{ad}\,\|\,x_f\,\|\,x_D\big), \qquad X_d' = x_l + \big(x_{ad}\,\|\,x_f\big), \qquad X_d = x_l + x_{ad} \]

where \(x_l\) is the armature leakage reactance, \(x_{ad}\) the direct-axis magnetising reactance, \(x_f\) the field leakage reactance and \(x_D\) the damper leakage reactance. Adding a branch in parallel can only reduce a reactance, so the ordering is automatic and needs no measurement to establish:

🔑
The ordering of the machine reactances
\[ X_d'' \;<\; X_d' \;<\; X_d \]

\(X_d''\) is the subtransient reactance (damper and field both active), \(X_d'\) the transient reactance (damper decayed, field still active), and \(X_d\) the direct-axis synchronous reactance (both decayed). Typical per-unit values on the machine rating are \(X_d''\approx 0.10\!-\!0.25\), \(X_d'\approx 0.15\!-\!0.40\), \(X_d\approx 1.0\!-\!2.0\).

X″d (subtransient) xl x_ad x_f x_D damper + field both hold flux first 2–3 cycles X′d (transient) xl x_ad x_f damper current has decayed tenths of a second Xd (synchronous) xl x_ad field current back to normal steady state
Rotor circuits drop out one by one, so the armature sees a rising reactance
The same three reactances, three different questions. Use \(X_d''\) for short-circuit current and breaker duty, because the first few cycles are what the equipment must survive. Use \(X_d'\) for transient stability (Chapters 27–29), because the machine swings on a time scale of tenths of a second. Use \(X_d\) for steady-state operation, excitation and the power-angle characteristic of Chapter 26. A number quoted without saying which of the three is meant is useless.
Section 21-5

The Decrement Curve and the Three Currents

Each of the three stages is entered and left exponentially, with a time constant set by the resistance of the rotor circuit that is decaying. Superposing them gives the armature current after a three-phase short circuit at the terminals of a machine running at no load with terminal voltage \(V_t\):

Armature current after a terminal three-phase short circuit
\[ i_a(t) = \sqrt2\,V_t\left[\left(\frac{1}{X_d''}-\frac{1}{X_d'}\right)e^{-t/T_d''} + \left(\frac{1}{X_d'}-\frac{1}{X_d}\right)e^{-t/T_d'} + \frac{1}{X_d}\right]\sin\!\left(\omega t + \alpha - \frac{\pi}{2}\right) \]

Read the bracket as an envelope. \(T_d''\), the subtransient short-circuit time constant, is of the order of \(0.03\) s — a couple of cycles — and is fixed by the damper winding resistance. \(T_d'\), the transient short-circuit time constant, is of the order of \(0.5\)–\(2\) s and is fixed by the field winding resistance. The armature resistance has been neglected, so the current lags the voltage by exactly \(90^\circ\); that is the \(-\pi/2\) in the sine.

Evaluating the envelope at three instants recovers three currents that the rest of the chapter uses constantly. At \(t=0\) all three exponentials are alive and the bracket telescopes to \(1/X_d''\). Once \(t\) is a few multiples of \(T_d''\) but still small compared with \(T_d'\), the first term has vanished and the second is still essentially unity, so the bracket is \(1/X_d'\). Long after \(T_d'\) only the constant survives.

🔑
The three rms symmetrical currents
\[ I'' = \frac{V_t}{X_d''} \quad(\text{subtransient}),\qquad I' = \frac{V_t}{X_d'} \quad(\text{transient}),\qquad I = \frac{V_t}{X_d} \quad(\text{steady state}) \]

Every one is an rms value of the symmetrical component only. The DC offset of Section 21-3 is superimposed on top of all three, with its own armature time constant \(T_A\), and its maximum value is \(i_{dc}^{max}=\sqrt2\,I''e^{-t/T_A}\).

This is also how the reactances are measured. Short-circuit a machine running at no load with a known terminal voltage, record the current, and remove the DC offset from each phase. Plot the resulting symmetrical envelope on semi-logarithmic paper. The last, flat part gives \(I\) and hence \(X_d\). Subtract that constant and the remainder is a straight line on the log plot whose intercept at \(t=0\) is \(I'-I\), giving \(X_d'\), and whose slope gives \(T_d'\). Subtract that in turn and the residue gives \(I''-I'\) and \(T_d''\). Each stripping operation isolates one exponential, exactly as in any multi-exponential decay.

t envelope I″I′I subtransient transient steady state T″d T′d envelope of the symmetrical current (DC offset removed) transient envelope extrapolated to t = 0
Stripping the envelope one exponential at a time gives X″d, X′d and Xd
Section 21-6

The Machine Model for a Fault Study

Sections 21-4 and 21-5 described a machine on no load. In practice the fault interrupts a system that was carrying load, and the model has to account for that. The device used is standard and deceptively simple: represent the machine during the subtransient period by a constant emf \(E''\) behind the constant reactance \(jX_d''\), and choose \(E''\) so that the model reproduces the prefault terminal conditions exactly.

Voltage behind subtransient reactance
\[ E'' = V^{(0)} + jX_d''\,I_L \qquad\text{(generator)}, \qquad\qquad E'' = V^{(0)} - jX_d''\,I_L \qquad\text{(motor)} \]

\(V^{(0)}\) is the prefault terminal voltage and \(I_L\) the prefault load current, taken positive out of a generator and into a motor — which is the whole reason for the sign difference. Once \(E''\) is computed the machine is a fixed source and the network is linear, so all the tools of Part 4 apply unchanged.

Synchronous motors and large induction motors must be included, and this is easy to forget. During a fault the system voltage collapses, the motor's internal emf momentarily exceeds its terminal voltage, and the machine feeds current into the fault instead of drawing it. A synchronous motor does this indefinitely; an induction motor does it for two or three cycles, until its rotor flux dies away, and is represented by an emf behind its locked-rotor reactance for exactly that reason. Neglecting motor contribution can understate the first-cycle fault current at an industrial bus by a third or more.

🔑
The fault-study network
Every synchronous machine becomes \(E''\) behind \(jX_d''\); every transformer, line and cable keeps the per-unit series impedance of Chapters 4 to 12; shunt admittance and static load are usually dropped.

Dropping line charging and static load is justified because both are small compared with the fault path: a fault impedance of \(0.1\) per unit dominates a load admittance of order \(1\) per unit. What may not be dropped is any machine, rotating load, or grounding impedance in the fault path.

Section 21-7

Symmetrical Faults by Thevenin and Superposition

With every source reduced to an emf behind a reactance, the faulted network is a linear circuit with several sources, and there are two ways to solve it. The direct way computes each \(E''\) from the prefault load flow, closes the switch representing the fault, and solves the resulting circuit; each machine's contribution then comes out complete, load current included. The second way is superposition, and it is the one that scales.

Split the faulted network into two networks whose responses add to the true one. The first is the prefault network, with all its sources and its known bus voltages \(V^{(0)}\) and load currents — nothing has happened in it yet. The second is the pure fault network: the same network with every source killed, driven by a single voltage source of value \(-V_k^{(0)}\) inserted at the fault point. Adding the two reproduces the faulted condition, because at the fault point the two sources \(V_k^{(0)}\) and \(-V_k^{(0)}\) sum to zero — which is precisely the statement that the bus has been shorted to the reference.

Superposition applied to a fault at bus \(k\)
\[ I_f = \frac{V_k^{(0)}}{Z_{th}+Z_f}, \qquad \text{(total current in any branch)} = \text{(prefault current)} + \text{(pure-fault current)} \]

\(Z_{th}\) is the Thevenin impedance of the passive network looking into the fault point, and \(Z_f\) is the fault impedance, zero for a bolted fault. The great convenience is that the pure fault network has no load, no generation and exactly one source, so it can be solved by ordinary series–parallel reduction or by current division. The great trap is that its currents are not the answer: they must be added back to the prefault currents branch by branch.

In hand calculation the addition is often skipped, and the justification is worth stating rather than assuming. Prefault load current at a bus is of the order of \(1\) per unit; the pure-fault current is of the order of \(1/Z_{th}\), which for a strong bus is five to twenty per unit. Adding a unit vector to a vector of length ten changes its magnitude by at most ten per cent, and usually much less because the two are nearly in quadrature — load current is close to real, fault current is almost purely inductive. Example 3 carries out both calculations so the size of the error can be seen.

Two idealisations, and what they cost. Setting every prefault voltage to \(1.0\angle 0^\circ\) per unit removes the need for a load flow and makes the whole network passive, so \(Z_{th}\) alone determines the fault current. It is accurate to a few per cent on a well-regulated transmission system, where voltages sit between \(0.95\) and \(1.05\) per unit. Neglecting prefault current on top of that is a second, independent approximation. Both are conservative in the sense that matters for ratings only when the prefault voltage is taken at its maximum — which is why fault studies for breaker selection commonly use \(1.05\) or \(1.1\) per unit rather than \(1.0\).
Section 21-8

The Z-Bus Method for a Fault at Any Bus

Series–parallel reduction works for a network of five branches and fails for one of five hundred, and it has to be repeated from scratch for every candidate fault location. Chapter 17 removed both objections. The bus impedance matrix was built there precisely so that \(Z_{kk}\) is the Thevenin impedance seen at bus \(k\) — one matrix, computed once, containing the Thevenin equivalent of every bus in the system simultaneously.

Recall the argument, since Part 5 leans on it repeatedly. In the pure fault network all sources are dead, and the only injection is \(-I_f\) at bus \(k\). By definition of \(\mathbf{Z}_{bus}\), the bus voltage changes are

Bus voltage changes in the pure fault network
\[ \begin{bmatrix}\Delta V_1\\ \Delta V_2\\ \vdots\\ \Delta V_n\end{bmatrix} = \mathbf{Z}_{bus}\begin{bmatrix}0\\ \vdots\\ -I_f\\ \vdots\\ 0\end{bmatrix} \quad\Longrightarrow\quad \Delta V_i = -Z_{ik}I_f \]

so that \(V_i = V_i^{(0)} - Z_{ik}I_f\) for every bus. One equation is still missing, and the faulted bus supplies it: there the voltage during the fault is the drop across the fault impedance, \(V_k = Z_f I_f\). Equating this to \(V_k^{(0)}-Z_{kk}I_f\) and solving closes the problem.

🔑
Complete solution of a three-phase fault at bus \(k\)
\[ I_f = \frac{V_k^{(0)}}{Z_{kk}+Z_f}, \qquad V_i = V_i^{(0)} - \frac{Z_{ik}}{Z_{kk}+Z_f}V_k^{(0)}, \qquad I_{ij} = \frac{V_i-V_j}{z_{ij}} \]

Only column \(k\) of \(\mathbf{Z}_{bus}\) is needed. Changing the fault location means reading a different column, not repeating a calculation. \(z_{ij}\) is the ordinary series impedance of the line joining buses \(i\) and \(j\) — an element of the primitive network, not of the matrix.

Three consequences follow at once. First, the faulted bus voltage is \(V_k = Z_f V_k^{(0)}/(Z_{kk}+Z_f)\), which is zero for a bolted fault as it must be. Second, the voltage depression at a remote bus \(i\) is in the ratio \(Z_{ik}/Z_{kk}\) — the off-diagonal entries measure how far the disturbance propagates, which is exactly the electrical distance between buses. Third, the arithmetic is self-checking: the currents arriving at bus \(k\) along every connected line, plus any generator connected there, must add up to \(I_f\), and Kirchhoff's current law must hold at every unfaulted bus. Example 4 uses both checks.

The flat prefault assumption simplifies this further. Setting every \(V_i^{(0)}=1.0\angle 0^\circ\) makes \(I_f = 1/(Z_{kk}+Z_f)\) and \(V_i = 1 - Z_{ik}/(Z_{kk}+Z_f)\), so a whole fault study reduces to reading one column and dividing. For an \(n\)-bus system this gives the fault level at all \(n\) buses from a single matrix, which is why the \(\mathbf{Z}_{bus}\) formulation, rather than the \(\mathbf{Y}_{bus}\) formulation of Chapter 16, is the natural one for fault work — and why load flow, which needs sparsity, uses the other.

Section 21-9

Short-Circuit Level and Circuit Breaker Selection

The number that summarises a bus in one figure is its short-circuit level or fault level: the apparent power that would be delivered into a bolted three-phase fault there, at the prefault voltage. With flat prefault voltage and per-unit quantities on a chosen base,

Short-circuit MVA
\[ \text{SC MVA at bus } k = \sqrt3\,\big|V_{L}\big|\,\big|I_{f,L}\big| \;=\; \big|V_{k,pu}^{(0)}\big|\,\big|I_{f,pu}\big|\times \text{MVA}_{base} \;=\; \frac{\text{MVA}_{base}}{\big|Z_{kk}\big|_{pu}} \]

with \(V_L\) in kV and \(I_{f,L}\) in kA. The last form is the useful one: fault level and Thevenin impedance are reciprocal descriptions of the same fact. A strong bus has small \(Z_{kk}\), holds its voltage well against load changes and motor starting, and demands expensive switchgear; a weak bus is the reverse. Every decision about adding generation, adding a line, or splitting a busbar moves both quantities together, and the tension between them runs through system planning.

Turning the fault level into a breaker specification requires the two currents identified in Section 21-1, and the two multipliers of Section 21-3.

🔑
The two breaker duties
\[ I_{momentary} \approx 1.6\,I'' \quad(\text{rms, first half cycle}), \qquad I_{interrupting} = (\text{multiplier})\times I'' \quad(\text{at contact parting}) \]

The momentary or close-and-latch duty is the mechanical and thermal stress on a closed breaker, and \(1.6\) is the asymmetry factor at \(X/R \approx 30\). The interrupting duty is what the arc must clear, three to eight cycles later, when part of the DC offset has decayed and the machines have moved from \(X_d''\) toward \(X_d'\); the multiplier is therefore smaller, and falls as the breaker gets slower.

Breakers are catalogued by nominal voltage, rated maximum voltage, continuous current, rated short-circuit current at rated maximum voltage, operating time, and a voltage range factor \(K\). The last is the ratio of rated maximum voltage to the lowest voltage at which the breaker retains full interrupting capability. Within that range the breaker's interrupting capability rises as the voltage falls, in inverse proportion, but never beyond \(K\) times the rated short-circuit current:

Interrupting capability at an operating voltage \(V\)
\[ I_{cap}(V) = \min\!\left(I_{rated}\times\frac{V_{max}}{V},\;\; K\,I_{rated}\right), \qquad \text{required: } I_{cap}(V)\ \ge\ I_{interrupting} \]

The corresponding statement in apparent power, which is how fault duty is usually quoted in a specification, is \(\text{SC interrupting MVA} = \sqrt3\,|V_{pf,L}|\,|I_{f,L}|\) with the prefault line voltage in kV and the interrupting current in kA. Chapter 25 works through the complete computation for a multi-machine system, Chapter 35 describes what happens inside the interrupter during those few milliseconds, and Chapter 36 sets the relay that gives the trip command in the first place.

Bus 1Bus 2Bus 3 G1 G2 j0.25 j0.25 j0.30 j0.20 j0.20 3-φ fault, I_f all values per unit on 100 MVA, 33 kV
The three-bus test system used in Examples 4 to 6
Section 21-10

Worked Examples

1 The DC offset in a switched feeder

Problem. An 11 kV, 50 Hz feeder of impedance \(0.6 + j6\;\Omega\) per phase is fed from a source of negligible impedance. A bolted three-phase fault occurs at its far end. Find the symmetrical rms current, the instant of closure that gives the largest offset, the first peak of the current, and the rms current at the end of the first half cycle.

Solution. The source phase voltage is \(V = 11000/\sqrt3 = 6350.9\) V. The magnitude and angle of the loop impedance are

Circuit constants
\[ Z=\sqrt{0.6^2+6^2}=6.0299\;\Omega, \qquad \theta=\tan^{-1}\frac{6}{0.6}=84.29^\circ, \qquad \frac{X}{R}=10 \]
\[ I = \frac{6350.9}{6.0299} = 1053.2\;\text{A (rms, symmetrical)}, \qquad \sqrt2\,I = 1489.5\;\text{A} \]

The offset is largest when \(\alpha-\theta=\pm90^\circ\), so \(\alpha = 84.29^\circ - 90^\circ = -5.71^\circ\): the fault must strike within a third of a millisecond of the voltage zero. The time constant is

Time constant and half-cycle decay
\[ \tau=\frac{L}{R}=\frac{X}{\omega R}=\frac{6}{2\pi(50)(0.6)} = 31.83\;\text{ms}, \qquad e^{-0.01/\tau}=e^{-0.3142}=0.7304 \]

Half a cycle after inception the exponential has fallen to \(73\,\%\) of its initial value, and the sinusoid is at its negative peak, so the two add:

First peak and momentary rms
\[ i_{peak}=1489.5\,(1+0.7304) = 2577\;\text{A} = 1.73\times\sqrt2\,I \]
\[ I_{rms}=1053.2\sqrt{1+2(0.7304)^2} = 1053.2\times 1.4377 = 1514\;\text{A} \]

Had the fault struck at \(\alpha=\theta=84.29^\circ\) instead, the current would have been a clean sinusoid of peak \(1489\) A from the first instant. The same fault, on the same feeder, differs by \(73\,\%\) in first-peak current according to nothing but the microsecond at which the insulation happened to fail.

2 Reading the three reactances off an oscillogram

Problem. A 20 MVA, 11 kV synchronous generator running on no load at rated terminal voltage is subjected to a bolted three-phase terminal fault. After the DC offset has been removed from the trace, the symmetrical envelope gives an initial rms current of 8.40 kA, a transient value extrapolated to \(t=0\) of 4.20 kA, and a steady value of 1.68 kA. Find \(X_d''\), \(X_d'\) and \(X_d\) in ohms and in per unit, and the maximum possible instantaneous current.

Solution. The machine is on no load, so the prefault terminal voltage is the rated value and \(V_t = 11000/\sqrt3 = 6350.9\) V per phase. Each reactance follows from its own current by \(X = V_t/I\):

Reactances in ohms
\[ X_d''=\frac{6350.9}{8400}=0.756\;\Omega, \qquad X_d'=\frac{6350.9}{4200}=1.512\;\Omega, \qquad X_d=\frac{6350.9}{1680}=3.780\;\Omega \]

Chapter 4 gives the base impedance on the machine rating, \(Z_{base}=11^2/20 = 6.05\;\Omega\), so

Reactances in per unit
\[ X_d''=\frac{0.756}{6.05}=0.125\;\text{pu}, \qquad X_d'=\frac{1.512}{6.05}=0.250\;\text{pu}, \qquad X_d=\frac{3.780}{6.05}=0.625\;\text{pu} \]

The base current is \(20\times10^6/(\sqrt3\times11000)=1049.7\) A, so the subtransient current is \(8400/1049.7 = 8.00\) per unit — which is just \(1/X_d''=1/0.125\), the check that the per-unit arithmetic is consistent.

The largest instantaneous current occurs when the phase concerned is fully offset. The AC peak is \(\sqrt2\times 8400=11879\) A, and if the armature time constant were long enough for no decay in the first half cycle the total would reach twice that, \(23.8\) kA. With a realistic \(X/R\) of \(30\) at the machine terminals the multiplier is \(1+e^{-\pi/30}=1.90\), giving \(22.6\) kA, and the rms momentary duty is \(1.6\times 8.40 = 13.4\) kA.

3 A generator feeding a motor: fault currents with and without prefault load

Problem. A 50 MVA, 20 kV generator with \(X_d''=0.20\) pu supplies, through a 50 MVA 20/66 kV transformer of \(0.10\) pu, a 66 kV line of \(10\;\Omega\), and a 50 MVA 66/18 kV transformer of \(0.10\) pu, a 25 MVA 18 kV synchronous motor with \(X_d''=0.20\) pu on its own rating. The motor is drawing its rated 25 MVA at 0.9 power factor lagging with its terminals at 1.0 per unit when a bolted three-phase fault occurs at those terminals. Find the subtransient fault current, and the contribution of each machine, with and without the prefault load current.

Solution. Take a system base of 50 MVA, with 20 kV in the generator zone, 66 kV on the line and 18 kV in the motor zone. The transformer ratios define the zones, so no reactance needs converting except the motor's, which is on a 25 MVA rating, and the line, which is in ohms:

Per-unit reactances on the 50 MVA base
\[ X_m'' = 0.20\times\frac{50}{25}=0.40\;\text{pu}, \qquad Z_{base,line}=\frac{66^2}{50}=87.12\;\Omega, \qquad X_{line}=\frac{10}{87.12}=0.1148\;\text{pu} \]
\[ X_{gen\;side} = 0.20+0.10+0.1148+0.10 = 0.5148\;\text{pu (generator emf to motor bus)} \]

The motor's rated 25 MVA is \(0.5\) per unit on the 50 MVA base, and at 0.9 lagging with the terminal voltage as reference the prefault current drawn into the motor is

Prefault load current
\[ I_L = 0.5\angle-\cos^{-1}(0.9) = 0.5\angle-25.84^\circ = 0.4500-j0.2179\;\text{pu} \]

Now build the two internal emfs. The motor absorbs \(I_L\), the generator delivers it:

Voltages behind subtransient reactance
\[ E_m'' = 1.0 - j0.40\,I_L = 1.0 - j0.40(0.4500-j0.2179) = 0.9128-j0.1800\;\text{pu} \]
\[ E_g'' = 1.0 + j0.5148\,I_L = 1.0 + j0.5148(0.4500-j0.2179) = 1.1122+j0.2317\;\text{pu} \]

With the fault applied, the motor bus is at zero potential, so each machine drives its own emf through its own reactance into the fault:

Contributions, prefault current included
\[ I_m'' = \frac{E_m''}{j0.40} = \frac{0.9128-j0.1800}{j0.40} = -0.4500-j2.2821\;\text{pu} \]
\[ I_g'' = \frac{E_g''}{j0.5148} = \frac{1.1122+j0.2317}{j0.5148} = 0.4500-j2.1604\;\text{pu} \]
\[ I_f'' = I_g''+I_m'' = -j4.4425\;\text{pu} \]

Now repeat by superposition, neglecting the prefault current. The passive network seen from the fault is \(j0.40\) in parallel with \(j0.5148\):

Thevenin route
\[ Z_{th}=j\frac{0.40\times0.5148}{0.40+0.5148}=j0.2251\;\text{pu}, \qquad I_f''=\frac{1.0}{j0.2251}=-j4.4425\;\text{pu} \]
\[ I_{m0}''=I_f''\frac{0.5148}{0.9148}=-j2.5000, \qquad I_{g0}''=I_f''\frac{0.40}{0.9148}=-j1.9425\;\text{pu} \]

The total is identical, as it must be — the load current circulates between the two machines and cancels in the sum. Restoring it branch by branch, \(I_g''=I_{g0}''+I_L\) and \(I_m''=I_{m0}''-I_L\), reproduces the first calculation exactly. The individual contributions differ by \(0.45\) per unit of real current, which changes \(|I_g''|\) from \(1.943\) to \(2.207\) and \(|I_m''|\) from \(2.500\) to \(2.326\): errors of \(12\,\%\) and \(7\,\%\) in the branch currents, and none at all in the fault current.

In amperes, the base current in the 18 kV motor zone is \(50\times10^6/(\sqrt3\times18000)=1603.8\) A, so the subtransient fault current is \(4.4425\times1603.8 = 7125\) A against a prefault load current of \(0.5\times1603.8=802\) A — a factor of nearly nine.

4 A three-bus fault study from the Z-bus

Problem. For the system of the figure in Section 21-9 — generators at buses 1 and 2 each behind \(j0.25\) pu, a tie of \(j0.30\) between buses 1 and 2, and lines of \(j0.20\) from bus 1 to bus 3 and from bus 2 to bus 3, all on a 100 MVA base — the building algorithm of Chapter 17 gives

Bus impedance matrix
\[ \mathbf{Z}_{bus}=j\begin{bmatrix} 0.15692 & 0.09308 & 0.12500\\ 0.09308 & 0.15692 & 0.12500\\ 0.12500 & 0.12500 & 0.22500 \end{bmatrix}\;\text{pu} \]

Find the fault current, all bus voltages and all line currents for a bolted three-phase fault at bus 3, and then at bus 1. Assume flat prefault voltages of \(1.0\angle0^\circ\).

Solution. Verify two entries first, because a wrong \(\mathbf{Z}_{bus}\) invalidates everything after it. Buses 1 and 2 are electrically identical, so a current injected at bus 3 divides equally and none flows in the \(j0.30\) tie. Bus 3 therefore sees two identical paths of \(j0.20+j0.25=j0.45\) in parallel, giving \(Z_{33}=j0.225\); and the voltage raised at bus 1 by \(1\) pu injected at bus 3 is \(0.5\times j0.25 = j0.125 = Z_{13}\). For \(Z_{11}\), look into bus 1 with the generator branch removed: \(j0.30\) in parallel with \(j0.40\) (the path \(1\!-\!3\!-\!2\)) is \(j0.1714\), plus \(j0.25\) for generator 2 gives \(j0.4214\), in parallel with generator 1's \(j0.25\) gives \(j0.15692\). Both agree.

Fault at bus 3. With \(Z_f=0\),

Fault at bus 3
\[ I_f=\frac{1.0}{j0.22500}=-j4.4444\;\text{pu}, \qquad V_3=0 \]
\[ V_1=V_2=1-\frac{0.12500}{0.22500}=1-0.5556=0.4444\;\text{pu} \]

The line currents follow from the bus voltages. By symmetry the tie carries nothing:

Line and generator currents
\[ I_{12}=\frac{0.4444-0.4444}{j0.30}=0, \qquad I_{13}=I_{23}=\frac{0.4444-0}{j0.20}=-j2.2222\;\text{pu} \]
\[ I_{G1}=I_{G2}=\frac{1.0-0.4444}{j0.25}=-j2.2222\;\text{pu} \]

The two line currents arriving at bus 3 sum to \(-j4.4444\), which equals \(I_f\); and at bus 1 the generator current \(-j2.2222\) leaves entirely down line 1–3. Both checks pass.

Fault at bus 1. Read column 1 instead:

Fault at bus 1
\[ I_f=\frac{1.0}{j0.15692}=-j6.3729\;\text{pu}, \qquad V_1=0 \]
\[ V_2=1-\frac{0.09308}{0.15692}=0.4068, \qquad V_3=1-\frac{0.12500}{0.15692}=0.2034\;\text{pu} \]
Currents into the faulted bus
\[ I_{G1}=\frac{1.0-0}{j0.25}=-j4.0000,\quad I_{21}=\frac{0.4068}{j0.30}=-j1.3559,\quad I_{31}=\frac{0.2034}{j0.20}=-j1.0170 \]
\[ \text{sum} = -j(4.0000+1.3559+1.0170) = -j6.3729 = I_f \;\;\checkmark \]

Kirchhoff's law at the unfaulted bus 3 is the second check: \((0.4068-0.2034)/j0.20 = -j1.0170\) flows in from bus 2 and exactly \(-j1.0170\) flows out to bus 1, with no injection at bus 3. Notice how much more severe the fault at bus 1 is — \(6.37\) pu against \(4.44\) pu — simply because a generator is connected directly there.

5 Fault impedance, and the short-circuit level of each bus

Problem. For the same three-bus system, repeat the fault at bus 3 with an arcing fault impedance of \(Z_f=j0.05\) pu, and state the short-circuit MVA and bolted fault current in kA at all three buses. The base is 100 MVA and the buses are at 33 kV.

Solution. The fault impedance simply adds to the diagonal entry:

Fault through an impedance
\[ I_f=\frac{1.0}{j(0.22500+0.05)}=\frac{1.0}{j0.27500}=-j3.6364\;\text{pu} \]
\[ V_3=Z_fI_f=(j0.05)(-j3.6364)=0.1818\;\text{pu}, \qquad V_1=V_2=1-\frac{0.12500}{0.27500}=0.5455\;\text{pu} \]

The consistency check is that \(V_3\) computed the other way, \(1-0.22500/0.27500 = 1-0.8182=0.1818\), gives the same answer. A fault impedance of only \(0.05\) pu — about \(0.54\;\Omega\) at 33 kV — reduces the fault current by \(18\,\%\) and leaves the faulted bus at nearly a fifth of nominal voltage, which is precisely why an impedance fault can be harder for a distance relay to see than a bolted one.

For the fault levels, the base current at 33 kV is \(I_{base}=100\times10^6/(\sqrt3\times33000)=1749.5\) A:

Bus\(|Z_{kk}|\) pu\(I_f=1/Z_{kk}\) pu\(I_f\) kASC MVA \(=100/Z_{kk}\)
10.156926.37311.15637
20.156926.37311.15637
30.225004.4447.78444

Bus 3, farthest from generation, is the weakest of the three. The cross-check \(\sqrt3\times33\times11.15 = 637\) MVA reproduces the table entry from the line quantities directly.

6 Choosing a breaker for bus 1

Problem. A breaker is to be selected for bus 1 of the same system, where \(I''=6.373\) pu = 11.15 kA and \(X/R\approx 30\). A candidate breaker is rated: nominal 33 kV, rated maximum voltage 38 kV, \(K=1.24\), rated short-circuit current 20 kA at 38 kV, five-cycle interrupting time. Determine the momentary and interrupting duties and check the breaker.

Solution. The momentary or close-and-latch duty uses the asymmetry factor of Section 21-3 at \(X/R=30\), which is \(\sqrt{1+2e^{-2\pi/30}}=1.62\), rounded to the standard \(1.6\):

Momentary duty
\[ I_{momentary}=1.6\times 11.15 = 17.8\;\text{kA (rms, asymmetrical)} \]
\[ i_{peak}=\sqrt2\,(1+e^{-\pi/30})\times11.15 = 2.69\times11.15 = 30.0\;\text{kA} \]

The interrupting duty is assessed five cycles later. Both generators are close to the fault, so a multiplier of \(1.0\) on the subtransient current is used here — a conservative choice, since by that time the machines have begun moving from \(X_d''\) toward \(X_d'\) and part of the DC offset has decayed:

Interrupting duty
\[ I_{interrupting}=1.0\times11.15=11.15\;\text{kA}, \qquad \text{SC interrupting MVA}=\sqrt3\times33\times11.15=637\;\text{MVA} \]

Now the breaker. Its capability at the 33 kV operating voltage is the smaller of the inverse-voltage value and the \(K\)-factor ceiling:

Breaker capability at 33 kV
\[ I_{rated}\frac{V_{max}}{V}=20\times\frac{38}{33}=23.0\;\text{kA}, \qquad K\,I_{rated}=1.24\times20=24.8\;\text{kA} \]
\[ I_{cap}= \min(23.0,\;24.8) = 23.0\;\text{kA} \;\;\ge\;\; 11.15\;\text{kA} \;\;\checkmark \]

The breaker interrupts \(23.0\) kA at 33 kV, equivalent to \(\sqrt3\times33\times23.0 = 1315\) MVA, against a required \(637\) MVA. Its close-and-latch rating, normally quoted as \(1.6\) times the maximum symmetrical interrupting capability, is \(1.6\times24.8=39.7\) kA against the \(17.8\) kA demanded. The breaker is comfortably adequate at both duties, which leaves room for the system to be strengthened later — a margin worth having, since every added generator or line raises the fault level at every bus.

Review

Chapter Summary

Only one fault is symmetrical

The three-phase fault keeps the network balanced, so per-phase analysis survives. It is 5 % of faults and sets most ratings.

The DC offset

\(i_{dc}=-\sqrt2(V/Z)\sin(\alpha-\theta)e^{-t/\tau}\) exists only to hold \(i(0)=0\). Maximum when the fault strikes at a voltage zero.

Asymmetry factors

Peak \(=\sqrt2 I(1+e^{-\pi R/X})\), rms \(=I\sqrt{1+2e^{-2\pi R/X}}\). At \(X/R=30\) the rms factor is 1.6.

Three reactances

\(X_d''<X_d'<X_d\), because damper and field leakage paths shunt the magnetising reactance until their currents decay.

Which one to use

\(X_d''\) for fault current and breaker duty, \(X_d'\) for transient stability, \(X_d\) for steady-state operation.

Superposition

Prefault network plus pure-fault network. \(I_f=V_k^{(0)}/(Z_{th}+Z_f)\); add prefault currents back branch by branch.

One column of Z-bus

\(I_f=V_k^{(0)}/(Z_{kk}+Z_f)\) and \(V_i=V_i^{(0)}-Z_{ik}I_f\) solve the whole network for a fault anywhere.

Fault level and breakers

SC MVA \(=\) MVA\(_{base}/|Z_{kk}|\). Momentary duty \(\approx 1.6I''\); interrupting duty is smaller and depends on breaker speed.

Practice

Practice Problems

Work in per unit throughout, on a stated base, and assume flat prefault voltages of \(1.0\angle0^\circ\) unless the problem says otherwise. Difficulty rises down the list.

  1. A 33 kV, 50 Hz source of negligible impedance feeds a line of \(1.2+j9\;\Omega\) per phase. A bolted three-phase fault occurs at the far end. Find the symmetrical rms current, the worst-case first peak, and the rms current at the end of the first half cycle.
  2. For the circuit of Problem 1, at what value of \(\alpha\) does the fault produce no DC offset at all? Show that the offsets in the three phases of that same fault sum to zero at every instant.
  3. A 60 MVA, 13.8 kV generator has \(X_d''=0.14\) pu, \(X_d'=0.22\) pu and \(X_d=1.10\) pu. It is on open circuit at rated voltage when a bolted three-phase terminal fault occurs. Find the subtransient, transient and steady-state rms currents in kA, and the maximum instantaneous current assuming \(X/R=25\).
  4. A 25 MVA, 11 kV generator with \(X_d''=0.15\) pu supplies a load of 20 MVA at 0.85 lagging with terminals at 1.0 pu. Compute \(E''\), then the subtransient fault current for a bolted three-phase fault at the terminals, both including and neglecting the prefault load current, and state the percentage error incurred by neglecting it.
  5. Two generators, 30 MVA with \(X''=0.15\) pu and 45 MVA with \(X''=0.20\) pu, both at 11 kV, operate in parallel on a common bus. Find the short-circuit MVA at that bus on a 100 MVA base, and the current each machine contributes to a bolted three-phase bus fault.
  6. For the three-bus system of Section 21-9, recompute \(\mathbf{Z}_{bus}\) with the \(j0.30\) tie between buses 1 and 2 removed, and find the fault current and all bus voltages for a bolted fault at bus 3. By how much does removing the tie change the fault level at bus 3, and at bus 1?
  7. A four-bus system has \(Z_{33}=j0.18\) pu and \(Z_{13}=j0.11\) pu on a 100 MVA base, with all buses at 132 kV. For a fault at bus 3 through \(Z_f=j0.04\) pu, find the fault current in kA, the voltage at bus 1, and the short-circuit MVA that a bolted fault at bus 3 would represent.
  8. A current-limiting reactor is to be installed at a 33 kV bus whose present fault level is 900 MVA, so as to reduce it to 600 MVA. Find the required reactor rating in ohms and in per unit on a 100 MVA base, and state what the installation costs in terms of steady-state voltage regulation at that bus.
Tip: before any fault calculation, write down which reactance each machine is contributing and on what base each per-unit value was quoted. Nearly every wrong answer in this subject comes from one of three places — a machine reactance left on its own MVA base instead of the system base, a prefault voltage taken as \(1.0\) when the question supplied a different one, or the subtransient reactance quietly replaced by the transient one. Chapter 4 exists to prevent the first; the second and third are matters of reading the question. The physics of Sections 21-2 to 21-5 is the easy part.