Load Characteristics, Tariffs and Power Factor Improvement
Electricity cannot be stored in bulk, so a power system must be built for the worst hour of the year and paid for by the average one — and almost every operating rule, every tariff and every capacitor bank in the network follows from that single awkward fact.
- How a load curve and a load duration curve carry the same information in two forms, and what the area under each one means.
- The defined factors — demand, load, diversity, plant capacity, plant use — and the algebraic relations that tie them together instead of leaving them as a list.
- Why the cost of serving a consumer splits into a part proportional to kW of maximum demand and a part proportional to kWh, and why every serious tariff mirrors that split.
- How the cost per unit falls as \(1/\text{load factor}\), which is the entire commercial argument for interconnection and off-peak pricing.
- Why a low power factor raises current, losses, regulation and equipment ratings, and how \(Q_c = P(\tan\phi_1-\tan\phi_2)\) sizes the correction.
- The derivation of the most economical power factor, \(\sin\phi_2 = B/A\), and why it is independent of the load and of the original power factor.
The Load Is Given, Not Chosen
Parts 2 to 6 of this book treated the load as a number. A line was analysed for a receiving-end power, a load flow was solved for fixed injections, a stability study assumed a constant \(P_m\). Part 7 removes that convenience. The load is not a number, it is a time series, it is set by millions of people acting independently, and the system operator has no control over it whatsoever.
That would be tolerable if electricity could be stockpiled. It cannot — not in the quantities a grid deals in. A power station is not a factory that builds to inventory; it is a machine that must produce, at every instant, exactly what is being consumed at that instant, because the alternative is a frequency excursion of the kind Chapter 33 studies. Generation therefore follows demand continuously, and demand varies by a factor of two or three over a single day.
Three consequences follow, and between them they account for most of what Part 7 is about.
Plant must be built for the peak. The installed capacity is fixed by the highest demand of the year, plus a reserve. Every megawatt of that capacity carries interest, depreciation, insurance and staffing whether it runs for eight thousand hours or for eight. Since the average demand is well below the peak, a large part of the investment is idle a large part of the time.
Efficiency suffers. An alternator and its turbine reach best efficiency near rated output. A single machine sized for the peak would spend the night at a fraction of its rating, at poor efficiency and high heat rate. The remedy is several smaller units, brought on and off as demand moves — which improves running cost but raises capital cost per kW and floor area, and creates the scheduling problem of Chapters 31 and 32.
Auxiliary plant must track the load. Raising output means raising the flow of fuel, air and feedwater in step. That calls for controls and margin in every auxiliary, and it is why a station's response rate is finite — the ramping constraint that reappears in unit commitment.
Load Curves and the Load Duration Curve
A load curve is the plot of load against time. Readings are taken half-hourly or hourly and plotted in sequence, giving a daily load curve; averaging the daily curves of a month at each hour gives the monthly load curve, used for setting rates; assembling the monthly curves gives the annual load curve, from which the annual load factor is computed.
Because the ordinate is power in kW and the abscissa is time in hours, the area under the curve is energy in kWh. This is the single most useful property of the diagram, and every quantity in Section 30-3 is read from it.
The highest point is the maximum demand of the day, which fixes the plant capacity required. The shape decides how many units are needed and in what order they run, and therefore the operating schedule of the station.
The load curve answers "what was the load at 3 p.m.?" A planner more often asks "for how many hours in the year was the load above 40 MW?", and reading that off a chronological plot means measuring dozens of separate intervals. Rearranging the same data in descending order of magnitude answers it at a glance. The result is the load duration curve: the highest load at the left, falling monotonically to the lowest at the right, with the abscissa now reading "hours for which the load equalled or exceeded this value".
No information is lost or gained in the rearrangement — only the chronology, which the planner does not need. In particular the area under the two curves is identical, because the same rectangles of energy have merely been sorted. Extending the abscissa from \(0\) to \(8760\) hours summarises an entire year of demand in one monotone curve, and that annual load duration curve is the working document for deciding how much of each kind of plant to build.
The Vocabulary of Demand
Four quantities describe a single consumer or a single station, and each is defined so that it can be read from the load curve without further data.
The connected load is the arithmetic sum of the continuous ratings of every piece of equipment on the installation. It is a nameplate figure and nothing more; nobody switches everything on at once.
The maximum demand is the greatest load actually drawn during a stated period, taken as an average over a defined interval — usually thirty minutes, because it is the thermal time constant of transformers and cables that matters, not an instantaneous spike. The averaging interval must always be quoted with the figure, since a shorter interval yields a larger maximum demand from the same load.
The ratio of the two defines the demand factor, which is what a designer actually uses to size a supply.
The average load over any period is the energy consumed divided by the duration, which is the area under the load curve divided by its base:
Finally, the ratio of average load to maximum demand is the load factor, and it is the most informative single number about any load whatsoever. Multiplying numerator and denominator by the duration \(T\) turns it into a ratio of areas, which is why it can be read off the diagram directly as the fraction of the enclosing rectangle that the load curve fills.
Equivalently, the load factor is the area under the load curve divided by the area of the rectangle that just contains it. Rearranging gives the relation used constantly in tariff work: \(\text{Units generated per annum} = \text{Max. demand}\times\text{L.F.}\times 8760\).
A high load factor means the plant is being used near its maximum most of the time. Since capacity is bought to meet the maximum demand, a high load factor spreads that fixed investment over more units of energy and lowers the cost of each — a statement made quantitative in Section 30-7. A low load factor means expensive plant standing idle.
Diversity, Capacity and Use Factors
The previous section described one load. A station serves many, and their peaks do not coincide: the domestic peak is in the evening, the industrial peak in mid-morning, the irrigation peak at night. The station therefore never has to supply the arithmetic sum of its consumers' individual maximum demands, and the ratio of the two measures how much the mismatch is worth.
Combining it with the demand factor gives the working formula for sizing a station: \(\;\text{Station MD}=\dfrac{\sum(\text{connected load}\times\text{demand factor})}{\text{diversity factor}}\).
The two factors work in the same direction. A large demand factor and a small diversity factor both push the station's maximum demand up, requiring more plant and more capital for the same energy sold. Deliberately mixing consumer classes on one station — some domestic, some industrial, some agricultural — raises the diversity factor and is one of the cheapest ways to reduce the capacity required per unit of energy delivered.
Two further ratios compare what the plant produced with what it could have produced. The plant capacity factor uses the installed capacity as the reference:
Dividing this by the load factor makes the relationship between the two explicit, and shows exactly what the gap between them measures:
So the plant capacity factor equals the load factor exactly when the maximum demand equals the plant capacity — that is, when there is no reserve at all. In every real station the capacity exceeds the maximum demand, so the capacity factor is the smaller of the two, and the gap between them is a direct measure of the reserve carried.
The plant use factor asks a narrower question: while the plant was actually running, how hard was it worked?
A peaking station may show a capacity factor of \(8\%\) and a use factor of \(80\%\): it is idle most of the year, but when it does run it runs nearly flat out. Quoting the capacity factor alone would make it look like a badly utilised asset rather than what it is — a machine bought for a small number of expensive hours.
| Factor | Definition | Range | What raises it |
|---|---|---|---|
| Demand factor | Max. demand / connected load | \(<1\) | Consumer switching more equipment on together |
| Load factor | Average load / max. demand | \(<1\) | A flatter load curve; off-peak use |
| Diversity factor | \(\sum\) individual MDs / station MD | \(>1\) | A wider mix of consumer types |
| Plant capacity factor | Average load / plant capacity | \(<\) L.F. | Less reserve, higher load factor |
| Plant use factor | Output / (capacity \(\times\) running hours) | \(<1\) | Running the plant only when it is needed at full output |
Types of Load and the Shape of the Curve
The load curve of a system is the sum of the curves of its consumer classes, and each class has a characteristic shape, load factor and weather sensitivity. Knowing which classes a station serves is what allows its curve to be predicted before it is measured.
Domestic load — lighting, fans, refrigeration, television, small water pumps. It is concentrated in the evening, with a smaller morning peak, and is almost dormant in the middle of the night. Its load factor is the worst of any class, typically \(10\%\) to \(12\%\), which makes it the most expensive class to serve per unit sold and explains why domestic tariffs are rarely the cheapest despite the small demands involved.
Commercial load — shop and office lighting, air conditioning, refrigeration in restaurants. It runs for more hours of the day than domestic load and so has a better load factor, but it is strongly seasonal, since air conditioning and space heating dominate the extremes of the year.
Industrial load — motors, furnaces, process plant. Magnitude varies from a few kilowatts in a small workshop to tens of megawatts in a steel or aluminium works; conventionally, small-scale industry is taken as up to about \(25\) kW, medium scale between \(25\) and \(100\) kW, and large scale above \(500\) kW. Industrial load is largely weather-independent and, where the plant runs in shifts, has by far the best load factor of any class. It is also the class with the worst natural power factor, for the reason set out in Section 30-8.
Municipal load — street lighting, water supply and drainage pumping. Street lighting is essentially constant through the hours of darkness. Water pumping is discretionary in timing, and utilities deliberately schedule it into the small hours, filling overhead tanks overnight and improving the system load factor at no cost to anyone.
Irrigation load — pump sets in agricultural areas, again supplied largely at night, typically for a block of about twelve hours, and again used as a filler for the overnight trough.
Traction load — trams, trolleybuses, suburban and main-line railways. It has the widest swing of any class, peaking sharply in the morning and again in the evening as people travel, and its rapid fluctuation makes it a difficult load for a generator to follow.
Meeting the Load: Base, Peak and Interconnection
Draw a horizontal line across the load duration curve. Everything below the line is demand that persists for the whole period — the base load. Everything above it appears for a few hours and vanishes — the peak load. The two have completely different economics, and separating them is the central idea of station planning.
Base-load energy is large in quantity and predictable in timing, so it should be produced by whatever plant has the lowest running cost per unit, however expensive that plant is to build: large thermal sets, nuclear stations, run-of-river hydro. Peak-load energy is small in quantity and needed at short notice, so it should come from plant that is cheap to build and quick to start, however expensive its fuel: gas turbines, diesel sets, pumped storage.
Attempting to serve the whole curve with one kind of plant is wrong in both directions. Base-load plant asked to follow the peak is cycled, which wears it and worsens its heat rate; peaking plant asked to carry the base burns expensive fuel for eight thousand hours a year. The split is quantified in Example 2, where the base unit finishes with a load factor of \(84\%\) and the peaking unit with \(17\%\) — and both figures are correct for their purpose.
The oldest and best method of improving the picture further is to stop treating a station as an island. An interconnected grid — several stations operating in parallel, which is the arrangement Chapter 2 described physically and Chapters 16 to 20 analysed electrically — delivers a list of benefits that all trace back to diversity:
| Benefit of interconnection | Mechanism |
|---|---|
| Exchange of peak loads | A station past its peak lends capacity to one approaching its own; neither needs plant for the sum |
| Use of older plant | Obsolete units are retained purely for the peak, where their poor efficiency costs little in energy terms |
| Economical operation | The most efficient sets in the whole pool carry the base — the dispatch problem of Chapter 31 |
| Increased diversity factor | The combined peak is less than the sum of the individual peaks |
| Reduced reserve capacity | One shared spinning reserve covers many stations instead of each carrying its own |
| Increased reliability | Loss of a unit is picked up by the pool rather than dropping load |
Every one of these is an economic argument, and every one of them is bought with the transmission network of Parts 2 and 3 and paid for with the stability constraints of Part 6. That trade — reliability and economy against synchronism — is the permanent tension in power system operation.
Cost Structure and the Tariffs Built On It
A tariff is not an arbitrary price list. It is an attempt to recover a cost, and the shape of the cost decides the shape of the tariff. The annual cost of supplying a consumer separates into three parts.
Fixed cost is independent of both the maximum demand and the energy: land, buildings, the cost of the distribution network's existence, management and metering.
Semi-fixed cost is proportional to the maximum demand, because that is what determines the size of the generator, transformer, switchgear and conductor that must be provided. It consists of interest and depreciation on that plant, plus a share of the salaries and maintenance that scale with plant size. It is incurred whether or not a single unit is drawn.
Running cost is proportional to the energy actually taken: fuel, lubricating oil, water, and the wear that scales with output.
Now divide by the units consumed to obtain the cost per unit, and eliminate the energy using the load-factor relation of Section 30-3, \(\text{kWh}=\text{MD}\times\text{L.F.}\times8760\). Ignoring the small constant \(a\):
The maximum demand cancels completely. What remains is a running cost \(c\) that every consumer pays alike, plus a capacity charge spread over the units taken — a term that varies as the reciprocal of the load factor. A consumer at \(\text{L.F.}=0.15\) carries more than five times the capacity charge per unit of one at \(\text{L.F.}=0.80\), for identical plant.
That single expression is the justification for the whole family of tariffs. Any tariff that charges for energy alone forces the high-load-factor consumers to subsidise the low ones; any tariff that charges for demand alone gives away energy. The honest structure has two terms, matching the two terms of the cost.
A workable tariff also has to satisfy several practical requirements at once: it must recover the total cost with a fair return, be simple enough that a consumer can understand and predict the bill, be cheap to meter, apportion the cost in proportion to the burden each consumer places on the system, and encourage behaviour that improves the system — a flatter curve and a better power factor.
| Tariff | Form | Recovers | Where used, and its defect |
|---|---|---|---|
| Simple (uniform) | Rs \(x\) per kWh, one rate | Energy only | Small consumers. Fails to charge for demand, so a low-load-factor consumer is subsidised |
| Flat rate | Different fixed rate per kWh for each class of load (lighting, power) | Energy, crudely class-adjusted | Recognises class differences but needs a separate meter per class |
| Block rate | First \(n_1\) units at \(x_1\), next \(n_2\) at \(x_2 < x_1\), and so on | Energy, with the demand charge buried in the first block | Domestic supply. Approximates a two-part tariff with one meter; the blocks are a crude proxy for load factor |
| Two-part | Rs \(b\) per kW of MD per year \(+\) Rs \(c\) per kWh | Demand and energy separately | The standard industrial tariff — exactly the cost structure above. Needs a maximum-demand indicator |
| Maximum demand | As two-part, but MD measured rather than assumed from connected load | Demand and energy | Large consumers; the measured MD makes it fair but the metering is more expensive |
| Power factor (kVA MD) | Demand charge levied on kVA rather than kW of MD | Demand, energy and reactive burden | Charges the consumer for the plant actually tied up. See Section 30-8 |
| Three-part | Fixed Rs \(a\) \(+\) Rs \(b\) per kW of MD \(+\) Rs \(c\) per kWh | All three cost components | The most complete form; the extra term \(a\) is the cost of merely being connected |
Power Factor: Why It Appears on the Bill
Chapter 3 defined the power triangle: for a three-phase load drawing line current \(I\) at line voltage \(V_L\), the apparent power is \(S=\sqrt3\,V_LI\), the active power is \(P=S\cos\phi\) and the reactive power is \(Q=S\sin\phi\). Only \(P\) does work. Yet every piece of equipment between the generator and the load is sized by \(S\) or by \(I\), never by \(P\), and that mismatch is what the power factor clause on a bill is about.
Invert the definition to see the damage. At fixed \(P\) and \(V_L\), the current a load draws is
A load at \(\cos\phi=0.7\) draws \(43\%\) more current than the same load at unity, and causes \(104\%\) more copper loss — the losses have roughly doubled for no extra useful output. Four separate costs follow from this one relation:
Larger conductors and plant. Cables, transformers, switchgear and alternators are rated in kVA, so serving \(P\) at a poor power factor ties up more capacity. An \(800\) kVA transformer delivers \(800\) kW at unity power factor and only \(560\) kW at \(0.7\).
Higher losses. The \(1/\cos^2\phi\) term above, paid for as fuel every hour of every year.
Worse regulation. Chapter 13 showed that the voltage drop along a line is approximately \(I(R\cos\phi + X\sin\phi)\); a larger current at a larger angle raises the drop on both counts, forcing larger conductors or more tap-changing.
Reduced system capability. The reactive current occupies the thermal rating of every element it passes through, so a system running at poor power factor reaches its limits while delivering less real power than it was built for.
The causes are structural rather than accidental. Most industrial load is induction motors, which draw magnetising current at close to \(90^\circ\) lagging; a motor's power factor is worst when it is lightly loaded, since the magnetising component is nearly constant while the load component falls. Arc and induction furnaces, welding sets, transformers on light load and discharge lighting all behave the same way. Left alone, an industrial installation settles at \(0.7\) to \(0.8\) lagging.
Since the utility's costs scale with kVA and its revenue under a simple tariff scales with kW, it recovers the difference by billing on the kVA maximum demand, or by adding a penalty below and a rebate above a stated power factor. Whichever form is used, the consumer's incentive is the same: raise \(\cos\phi\).
Improvement, and the Most Economical Power Factor
Correction means supplying the load's reactive demand locally instead of drawing it over the network. A capacitor connected in parallel with the load draws a leading current that cancels part of the lagging current the load takes; the active component is untouched, so \(P\) stays fixed and the triangle collapses inward.
Work in reactive power directly. Before correction the load draws \(Q_1 = P\tan\phi_1\); after correction the network must supply only \(Q_2 = P\tan\phi_2\). The difference is what the capacitor provides.
with \(\phi_1=\cos^{-1}(\text{original p.f.})\) and \(\phi_2=\cos^{-1}(\text{target p.f.})\). The active power \(P\) appears in both, so the kVAr required is directly proportional to the load — which is why correction is applied in switched steps that follow the load rather than as one fixed bank.
Three devices supply the leading kVAr, and the choice between them is a matter of size and duty. Static capacitors are cheap, have negligible losses, need almost no maintenance and can be switched in steps; against that, they are damaged by over-voltage, have a limited life, and — since \(Q\propto V^2\) — deliver least reactive power exactly when the voltage has sagged and it is most needed. Synchronous condensers are over-excited synchronous motors running on no load; they give continuously variable output of either sign and support the voltage smoothly, but they have rotating losses, need starting equipment and are only economic in large sizes. Phase advancers are fed into the rotor circuit of a wound-rotor induction motor to supply its magnetising ampere-turns at slip frequency, correcting the motor at source. Chapter 34 returns to all of these as instruments of voltage control rather than of billing.
The bank itself is sized from the kVAr. For a delta-connected three-phase bank across a line voltage \(V_L\), each of the three capacitors sees the full line voltage, so
The delta connection needs one third the capacitance for the same kVAr, at the price of full line-voltage insulation on each unit — the same trade that appears whenever a three-phase bank is connected either way.
How far should the correction be taken? Not to unity. Improving the power factor saves money on the demand charge but costs money in capacitors, and beyond a certain point the second effect wins. The optimum can be found exactly, and the answer is remarkably clean.
Let a consumer take \(P\) kW at \(\cos\phi_1\), let the annual maximum-demand charge be Rs \(A\) per kVA, and let the annual cost of the correction plant — interest and depreciation on the capacitors — be Rs \(B\) per kVAr. Assume the load is steady, so the maximum demand in kVA is \(P/\cos\phi_2\) after correction. The total annual cost as a function of the corrected angle is
Differentiate with respect to \(\phi_2\), remembering that \(\phi_1\) and \(P\) are constants:
Neither \(P\) nor \(\phi_1\) survives the differentiation. The optimum power factor depends only on the ratio of the capacitor's annual cost per kVAr to the utility's demand charge per kVA — a property of the tariff and the equipment market, not of the consumer. Every consumer under the same tariff should correct to the same power factor, and only the size of the bank differs.
The second derivative is positive at this point, so it is a minimum; and since \(B < A\) in any realistic case, \(\sin\phi_2 = B/A\) always has a solution. Unity power factor would require \(B=0\), which is to say free capacitors.
The minimum is a shallow one, and that matters practically. For the numbers of Example 6 the total annual cost varies by less than \(0.4\%\) between \(\cos\phi_2 = 0.90\) and \(0.95\), so a designer may choose a standard bank size anywhere in that range with no real penalty — but pushing on to \(0.99\) costs more than leaving the power factor uncorrected.
Worked Examples
Problem. A station's load on a given day is \(20\) MW from 00:00 to 06:00, \(40\) MW to 10:00, \(50\) MW to 12:00, \(35\) MW to 14:00, \(40\) MW to 18:00, \(60\) MW to 20:00, \(50\) MW to 22:00 and \(30\) MW to midnight. The installed capacity is \(75\) MW. Find the units generated, the average load, the load factor, the plant capacity factor and the reserve capacity.
Solution. The energy is the area under the curve, computed block by block:
The relation of Section 30-4 checks the two factors against each other: \(\text{Plant C.F.}/\text{L.F.} = 0.494/0.618 = 0.80\), which is exactly \(\text{MD}/\text{capacity}=60/75\). Since the plant ran for all \(24\) hours the plant use factor equals the capacity factor here; had it shut down overnight the use factor would have been higher.
Problem. For the day of Example 1, a \(40\) MW base-load unit is to carry as much as it can, the balance being met by peaking plant. Find the energy taken by each, the peaking capacity required, and the load factor of each unit.
Solution. Sort the loads in descending order to form the load duration curve: \(60\) MW for \(2\) h, \(50\) MW for \(4\) h, \(40\) MW for \(8\) h, \(35\) MW for \(2\) h, \(30\) MW for \(2\) h and \(20\) MW for \(6\) h. The base unit supplies \(\min(\text{load},40)\) at every hour — the area below the \(40\) MW line:
The peaking plant must cover the excess above \(40\) MW, whose largest value is \(60-40=20\) MW. The two load factors are then
Ninety-one per cent of the day's energy is carried by a unit running at \(84\%\) load factor, where an expensive, efficient machine earns its capital cost back. The remaining nine per cent needs \(20\) MW of capacity used at \(17\%\) — plant that must be cheap to buy, whatever its fuel costs.
Problem. A substation supplies four consumers with connected loads of \(100\), \(80\), \(60\) and \(40\) kW and demand factors of \(0.6\), \(0.5\), \(0.8\) and \(0.9\) respectively. The measured maximum demand on the substation is \(140\) kW and the annual load factor is \(0.45\). Find the diversity factor, the overall demand factor, and the units supplied per annum.
Solution. Each consumer's maximum demand is its connected load times its demand factor:
Without diversity the substation would have needed \(184\) kW of firm capacity instead of \(140\) — a quarter more plant, transformer and switchgear for exactly the same \(552{,}000\) units sold. That saving is why a utility mixes consumer classes on a feeder deliberately.
Problem. A two-part tariff charges Rs \(1200\) per kW of maximum demand per annum plus Rs \(3.50\) per kWh. Two consumers each have a maximum demand of \(100\) kW; the first has an annual load factor of \(0.15\), the second of \(0.80\). Compare their overall cost per unit.
Solution. Both pay the same demand charge of \(100\times1200 = \text{Rs }120{,}000\) per year, because both tie up the same plant. The energy each takes differs by more than five to one:
The formula of Section 30-7 gives the same answers without the intermediate arithmetic. The demand-charge contribution per unit is \(b/(8760\times\text{L.F.})\), which is \(1200/1314 = \text{Rs }0.913\) for A and \(1200/7008 = \text{Rs }0.171\) for B; adding the running charge of Rs \(3.50\) reproduces both figures exactly. Consumer A pays \(20\%\) more per unit, and the entire difference is the capacity charge spread over fewer units.
Problem. A factory draws \(500\) kW at \(0.75\) lagging from a \(700\) kVA transformer. Find the capacitor rating needed to raise the power factor to \(0.95\) lagging, the kVA released, and the additional active load the transformer could then carry.
Solution. The two angles and their tangents:
Before correction the \(700\) kVA transformer was \(95\%\) loaded: only \(33.3\) kVA of headroom remained, worth just \(25\) kW at a power factor of \(0.75\). After correction, at \(0.95\) power factor it can deliver \(700(0.95) = 665\) kW, so a further \(165\) kW of load can be connected without a larger transformer. A capacitor bank costing a fraction of a new transformer has bought a third more capacity out of the existing one — which is usually a stronger argument for correction than the demand charge itself.
Problem. A consumer takes a steady \(400\) kW at \(0.8\) lagging. The maximum-demand charge is Rs \(1500\) per kVA per annum, and the capacitors cost Rs \(600\) per kVAr per annum in interest and depreciation. Find the most economical power factor, the capacitor rating, and the annual saving.
Solution. Apply the result of Section 30-9 directly:
Test the optimum by trying neighbouring values. At \(\cos\phi_2=0.90\) the total is \(666{,}667+63{,}763=\text{Rs }730{,}430\); at \(0.95\) it is \(631{,}579+101{,}116=\text{Rs }732{,}695\); at \(0.99\) it is \(606{,}061+145{,}805=\text{Rs }751{,}866\), which is worse than not correcting at all. The optimum is genuine, it is shallow between \(0.90\) and \(0.95\), and it is a long way from unity.
Chapter Summary
Area under the load curve = kWh; average load = that area divided by the period.
The load duration curve has the same area as the load curve and answers "for how many hours?".
Average / maximum demand; units per annum \(=\text{MD}\times\text{L.F.}\times8760\).
\(\sum\)MD / station MD \(>1\); station MD \(=\sum(\text{connected}\times\text{demand factor})/\text{D.F.}\)
Plant C.F. / L.F. \(=\) MD / capacity; the gap between them measures the reserve.
Cost per unit \(= b/(8760\,\text{L.F.}) + c\) — the reason every real tariff has two parts.
\(I\propto1/\cos\phi\), losses \(\propto1/\cos^2\phi\), and every rating is in kVA.
\(Q_c=P(\tan\phi_1-\tan\phi_2)\); the economic optimum is \(\sin\phi_2=B/A\).
Practice Problems
Take a year as \(8760\) hours throughout. Where a tariff is given in rupees the numbers are illustrative; the method is what is being tested.
- A station's daily load is \(30\) MW for \(8\) hours, \(55\) MW for \(6\) hours, \(70\) MW for \(4\) hours and \(45\) MW for the remaining \(6\) hours. Find the units generated, the average load and the daily load factor. If the installed capacity is \(90\) MW, find the plant capacity factor and the reserve capacity.
- For the load of Problem 1, sketch the load duration curve and determine the energy that would be supplied by a \(45\) MW base-load unit, the peaking capacity required, and the load factor of each unit.
- A generating station has a maximum demand of \(25\) MW, a load factor of \(0.60\), a plant capacity factor of \(0.50\) and a plant use factor of \(0.72\). Find the annual energy generated, the reserve capacity and the number of hours for which the plant was in operation.
- Five consumers with connected loads of \(120\), \(90\), \(75\), \(60\) and \(45\) kW have demand factors of \(0.55\), \(0.65\), \(0.70\), \(0.80\) and \(0.85\). If the diversity factor at the substation is \(1.35\), find the substation maximum demand and the overall demand factor. If the annual load factor is \(0.40\), find the units supplied.
- A two-part tariff charges Rs \(900\) per kW of maximum demand per annum plus Rs \(4.00\) per kWh. Find the overall cost per unit at load factors of \(0.20\), \(0.40\) and \(0.75\), and show that the three results follow the relation \(b/(8760\,\text{L.F.})+c\).
- A consumer's maximum demand is \(200\) kW at \(0.72\) lagging. The utility bills Rs \(1800\) per kVA of maximum demand per annum. Find the annual saving if the power factor is raised to \(0.92\), and the capacitor rating required.
- For the consumer of Problem 6, capacitors cost Rs \(650\) per kVAr per annum in interest and depreciation. Find the most economical power factor, the capacitor rating at that value, and the net annual saving. Compare with the result of Problem 6 and comment.
- A \(415\) V, \(50\) Hz, three-phase load of \(150\) kW at \(0.70\) lagging is to be corrected to \(0.95\) lagging. Find the kVAr required and the capacitance per phase for both a star-connected and a delta-connected bank.